On the afternoon of August 4, comrade Le Tien Chau, Member of the Party Central Committee, Secretary of the City Party Committee, Head of the City's National Assembly Delegation went on a field survey [...]

On the afternoon of August 4, Comrade Le Tien Chau, Member of the Party Central Committee, Secretary of the City Party Committee, Head of the City's National Assembly Delegation went on a field survey of a number of projects in the western area of the city.
Along there were members of the Standing Committee of the City Party Committee: Hoang Quoc Thuong, Standing Deputy Secretary of the Party Committee of the City Party agencies; Le Trung Kien, Head of Hai Phong Economic Zone Management Board; Dao Trong Duc, Chief of the City Party Committee Office; Bui Van Thang, Director of the Department of Agriculture and Environment and Mr. Tran Van Quan, Member of the City Party Committee, Vice Chairman of the City People's Committee; Representatives of leaders of relevant departments, branches, units and localities.
In the working program, Secretary of the City Party Committee Le Tien Chau and the Working Group surveyed the progress of implementing works and projects: Cong Hoa Industrial Park; Investment plan for the road connecting National Highway 37 with the riverside road of Dong Trieu city; Tan An bridge construction project and National Highway 18 access road; Plan to connect Gia Binh airport with Lach Huyen port and the northern provinces of the city to develop the economic and urban space in the northern region of the city; project to renovate, repair and upgrade old buildings and add fire prevention and fighting systems at Hai Duong General Hospital; Cultural and sports complex in the West of the city and a high-speed route connecting the East and West of the city.
After directly surveying the reality and listening to representatives of the investor as well as leaders of departments, departments and branches of the city reporting, proposing recommendations and solutions to implement works and projects, giving instructions at inspection points, Comrade Secretary of the City Party Committee Le Tien Chau emphasized: For the Cong Hoa Industrial Park expansion project phase 2 (invested by Vietnam Rubber Industrial Park and Urban Development Joint Stock Company), the city welcomes and supports The household advocates expanding the project scale to help attract more new investors.
Comrade Secretary of the City Party Committee assigned the Hai Phong Economic Zone Management Board and the city's departments and branches to support and create favorable conditions in resolving administrative procedures, helping investors strive to start the project no later than in the first quarter of 2026. Regarding the proposal to build housing for experts and social housing in the industrial park to serve experts and workers coming to work in the industrial park, city leaders agreed and noted that the investor should implement the right purpose, commitment, strict management and not let any changes occur. For recommendations related to investment in rainwater and wastewater drainage systems; Providing clean water and electricity for industrial park operations, the investor closely coordinates with the Hai Phong Economic Zone Management Board and city departments and branches to get the best results.Guide and implement in accordance with instructions and legal regulations, ensuring that the industrial park operates at its best, attracting more domestic and foreign businesses and corporations to invest.
Regarding the investment plan for the road connecting National Highway 37 with the riverside road of Dong Trieu city, the Secretary of the City Party Committee basically agreed with the proposals and recommendations of the investor's representative. At the same time, direct the City People's Committee to work soon with Quang Ninh province to unify the policy of connecting and synchronously investing in projects, promoting investment efficiency.
>At the Tan An bridge and National Highway 18 construction project, the City Party Secretary encouraged the investor and units participating in the construction. To ensure completion and putting the project into operation on schedule as committed (December 31, 2025), he requested the investor to coordinate with the People's Committee of Chu Van An ward to urgently complete all site clearance work to hand over the construction unit as soon as possible. On the part of construction contractors, it is necessary to overcome difficulties, mobilize maximum human resources and equipment, and deploy construction solutions to compensate for the slow volume due to the impact of high construction material prices and lack of clean construction sites in recent times. The Secretary of the City Party Committee also noted that completing progress along with ensuring quality and technical requirements.
Survey of the city's key transportation infrastructure development project, including a high-speed route connecting the East - West areas of the city and a high-speed route connecting Gia Binh Airport with Lach Huyen Port. Comrade Secretary of the City Party Committee Le Tien Chau emphasized that these are two strategic traffic routes, contributing to effectively connecting the Eastern and Western economic regions of the city, exploiting the maximum potential of the national infrastructure system such as: Lao Cai - Hanoi - Hai Phong high-speed railway; Gia Binh airport; Hai Phong international gateway port at Lach Huyen and Nam Do Son Port... Along with that, the Southern Coastal Economic Zone and the new generation Free Trade Zone will create a breakthrough in regional connectivity, expand development space, increase space and form new economic zones.New growth driving force for the city in the coming period.
Comrade Secretary of the City Party Committee assigned the City People's Committee to urgently research and propose specific policies and investment plans; At the same time, organize a thorough assessment of investment efficiency and financial plans for each project to ensure efficiency, feasibility and compatibility with the overall development plan. At the same time, review and adjust the overall city planning, especially the planning of industrial, urban, service and logistics zones, to meet development requirements in the new situation.
For recommendations and proposals to adjust the total investment of the project to renovate, repair and upgrade old building blocks and add fire prevention and fighting systems at Hai Duong General Hospital, the City Party Secretary emphasized that city leaders support the policy of investing and developing medical infrastructure, thereby actively contributing to caring for and improving people's health. He assigned the City People's Committee and relevant departments and branches to research, balance, and arrange budgets to implement items so that the project can start as soon as possible. The Secretary of the City Party Committee noted that in addition to implementing investment projects and upgrading infrastructure and modern machinery and equipment, Hai Duong General Hospital needs to constantly pay attention to improving its professional qualifications and service attitude.of medical staff and doctors; Actively coordinate and cooperate with hospitals in Hanoi city as well as major hospitals in the city to transfer new and specialized techniques, thereby improving the effectiveness of the quality of medical examination, treatment, and health care for the city's people.
For the West City Cultural and Sports Complex project, the Secretary of the City Party Committee acknowledged the enthusiasm and efforts of agencies and units in building and proposing plans. At the same time, assign the City People's Committee, departments and branches to research and propose investment plans to ensure compliance with planning and investment efficiency./.