(Haiphong.gov.vn) - On the morning of February 29, Vice Chairman of the City People's Committee Nguyen Duc Tho inspected the progress of the road construction investment project from [...]

(Haiphong.gov.vn) - On the morning of February 29, Vice Chairman of the City People's Committee Nguyen Duc Tho inspected the progress of the implementation of the investment project to build a road from the Coastal Road (Km1+00) to Van Bun Junction, Ly Thai To Street (Do Son district). Accompanied by representatives of leaders of relevant departments, branches and localities.

Vice Chairman of the City People's Committee Nguyen Duc Tho inspected the site clearance work in Minh Duc ward.
The route has a length of 6.2km passing through Minh Duc, Ngoc Xuyen, Van Huong wards (Do Son district). The project will be implemented from 2019 to 2024, with a total investment of nearly 960 billion VND from the city budget. When completed, the Project will create an economic - technical - urban corridor in the Northwest - Southeast direction connecting Do Son tourist area with the city center and creating conditions for the western wards of Do Son district to restructure towards urbanization, creating momentum for the development of commercial, service, and tourism activities and attracting capital from investors in residential land, production, business, and tourism services in accordance with the content of the master plan for economic development. – Do Son district society.
>The area in Minh Duc ward has not yet completed site clearance work.
The total area of land acquisition and clearance for project implementation is 16.76 hectares for 341 households and 9 organizations in 3 wards of Ngoc Xuyen, Van Huong, and Minh Duc. In particular, Ngoc Xuyen ward has completed site clearance of all related areas. Minh Duc Ward has completed payments to 70 agricultural land households and 01 organization, 47/67 residential land households received compensation, and has filed enforcement documents for 7 households. In Van Huong ward, 111/138 households have received compensation, 27/138 households have not received money, the district has filed enforcement documents for 10 households. The total volume of site clearance to date has reached 97.12% of the area.
>Vice Chairman of the City People's Committee Nguyen Duc Tho inspected the site clearance work in Van Huong ward.
Regarding construction work, the project has completed the construction bidding package for the 110KV line moving item, and is implementing the construction bidding package for the transportation and technical infrastructure items, with the construction volume reaching about 37.55% of the volume.

Vice Chairman of the City People's Committee Nguyen Duc Tho gave a directive speech.
After inspecting the field and listening to reports from departments, branches, localities and units; Vice Chairman of the City People's Committee Nguyen Duc Tho assessed that the progress of site clearance for the project is currently slow compared to the set requirements. According to the plan, the project implementation time is only 10 months, so the Vice Chairman requested the Project Management Board, contractors and supervision consultants to urgently review the construction progress and clearly define the responsibilities of each unit.
For site clearance, the Vice Chairman of the City People's Committee requested the Project Management Board to direct contractors to immediately access the handed over sites, proceed with dismantling, and prepare for construction. For positions that have received money but have not yet handed over the premises, there is a plan to support construction contractors. There are 47 households that have not yet handed over their premises, requesting the district to focus on completing full enforcement documents and reporting to the City People's Committee.
The Vice Chairman of the City People's Committee requested Do Son district to strengthen its role in management and supervision, during the construction process, to limit the impact on the works of surrounding households, and to minimize the impact on the living environment of the people. At the same time, we request that Do Son district pay attention to directing site clearance work in accordance with the law. The Vice Chairman also noted that all land funds on both sides of the route have been cleared and must be strictly protected, not allowing encroachment to occur and cause loss of aesthetics.