(Haiphong.gov.vn) - On the morning of February 28, Vice Chairman of the City People's Committee Le Khac Nam went on a field trip to inspect and listen to progress reports on the implementation of component projects under the […]

(Haiphong.gov.vn) – On the morning of February 28, Vice Chairman of the City People's Committee Le Khac Nam went on site to inspect and listen to progress reports on the implementation of component projects under the Investment Program to build parks, flower gardens, and green trees in the districts, period 2021-2025.

Check out the An Da Temple flower garden project, Ngo Quyen district.
According to the Program, in the period 2021-2025, the city will invest in 62 additional flower gardens for the 7 districts, of which 9 parks and flower gardens have been completed; The remaining parks and flower gardens are being focused on implementation from now until 2025.

An Da Temple flower garden project, Ngo Quyen district is actively under construction.
As of February 26, 2024, the Department of Finance has completed appraisal of investment policies for 23 projects. The City People's Committee has approved investment policies for 20 projects. The People's Committees of the districts have completed the preparation of Feasibility Study Reports and Technical Economic Reports for 13 projects. The Department of Construction has completed the appraisal of 12 Feasibility Study Reports and Technical Economic Reports, temporarily suspending appraisal for 01 project due to lack of detailed planning at 1/500 scale.

>Check out the Flower Garden Project in Dang Hai Ward, Hai An District.
In general, up to this point, the progress of projects is still slow, mainly due to the preparation, appraisal, and approval of adjusted planning of 1/2000, detailed planning of 1/500 scale; Supplementing land use plans and converting land use purposes. People's Committees of districts face many difficulties and obstacles in compensation and support work, especially the lack of resettlement land fund to serve site clearance for projects.
>Vice Chairman of the City People's Committee Le Khac Nam requested units to review all park, flower garden, and green tree projects in the city.
After inspecting the reality and listening to reports from departments, branches and localities, Vice Chairman of the City People's Committee Le Khac Nam requested units to review all park, flower garden and tree projects in the city. If they are not suitable in terms of location and use, they must report to the city for consideration and adjustment. If choosing to move to a new location, it must ensure all conditions and meet people's usage requirements, the Vice Chairman emphasized.
>Vice Chairman of the City People's Committee Le Khac Nam assigned the Departments to inspect the reality and report to advise the city before March 8, 2024.
The Vice Chairman of the City People's Committee assigned the Departments of Natural Resources and Environment, Department of Construction, Department of Planning and Investment to coordinate with districts to urgently resolve land problems; planning. Request the Departments to conduct an actual inspection to have a report to advise the city before March 8, 2024./.