– On the morning of July 5, leaders of Hai Phong city and leaders of Quang Ninh province organized an inspection of the progress of the […]

– On the morning of July 5, leaders of Hai Phong city and leaders of Quang Ninh province organized an inspection of the progress of the investment project to build Ben Rung bridge connecting Thuy Nguyen district, Hai Phong city with Quang Yen town, Quang Ninh province and the investment project to build Lai Xuan bridge, renovate and expand provincial road 352.

Leaders of Hai Phong city and Quang Ninh province inspect the field at the Ben Rung Bridge Construction Investment Project.
On the side of Hai Phong city, there were comrades in attendance: Le Tien Chau, Member of the Party Central Committee, Secretary of the City Party Committee; Nguyen Van Tung, Deputy Secretary of the City Party Committee, Chairman of the City People's Committee; Pham Van Lap, Chairman of the City People's Council; Leaders of relevant departments, functional branches and localities.
On the side of Quang Ninh province, there were the participation of comrades: Nguyen Xuan Ky, Member of the Party Central Committee, Secretary of the Provincial Party Committee, Chairman of the Provincial People's Council; Cao Tuong Huy, acting Chairman of the Provincial People's Committee; and leaders of relevant departments, branches and localities of Quang Ninh province.

Field inspection at the Ben Rung Bridge Pathway Project.
According to the report of the Hai Phong Traffic Construction Investment Project Management Board, up to this point, the Ben Rung Bridge Construction Investment Project is being implemented closely according to the proposed plan, the forest land area on the Quang Ninh side has been handed over. Currently, the Project Management Board is directing contractors to focus resources and speed up progress. Contractors have completed 340/380 bored piles, under construction at 33/38 abutment and pillar locations; Estimated implementation volume reaches about 55% of contract value...striving to basically complete the construction of Ben Rung bridge before Lunar New Year 2024.

Work scene.
Comrade Nguyen Van Tung, Deputy Secretary of the City Party Committee, Chairman of the City People's Committee spoke at the meeting.
Comrade Cao Tuong Huy, acting Chairman of Quang Ninh Provincial People's Committee, spoke at the meeting.
For the new construction project of Lai Xuan bridge and renovation and expansion of provincial road 352, related to the land acquisition area of 34.18 hectares serving the Hai Phong project, Thuy Nguyen district People's Committee is currently carrying out compensation and site clearance work for 8 communes, including: Thien Huong, My Dong, Kien Bai, Chinh My, Cao Nhan, Quang Thanh, Ky Son and Lai Xuan. On the Quang Ninh side, the land recovery area is about 3.6 hectares involving about 75 households. Currently, the People's Committee of Dong Trieu town and Gia Duc commune are organizing an inventory.
Regarding construction work, contractors are carrying out the work of drilling bored piles for 2 main pillars in the middle of the river T8 and T9 (30/130 piles completed); Organize excavation and foundation construction; Installing vertical sewers for the renovation and expansion of provincial road 352...

Panoramic view of the construction project of Ben Rung Bridge.
Through field inspection and listening to opinions expressed at the meeting, Mr. Nguyen Xuan Ky, Secretary of the Provincial Party Committee - Chairman of the People's Council of Quang Ninh province praised the efforts of Quang Yen town and expressed his impression of the fast construction progress of the Hai Phong Traffic Construction Investment Project Management Board. Noting that the implementation progress commitments between the parties are well-founded, the Secretary of the Quang Ninh Provincial Party Committee clearly stated that the completion milestone of the Ben Rung bridge road project connecting to provincial road 338 in Quang Yen town must be completed on April 30, 2024, completed simultaneously with the Ben Rung bridge project.

Comrade Nguyen Xuan Ky, Secretary of the Provincial Party Committee - Chairman of the People's Council of Quang Ninh province spoke at the meeting.
Emphasizing the significance of the two bridge projects in connecting inter-regional traffic, the Secretary of the Quang Ninh Provincial Party Committee also informed that when Ben Rung and Lai Xuan bridges are completed and put into operation, Quang Ninh province will basically complete the high-speed riverside route, creating a synchronous strategic transportation system, a new development space for Quang Ninh province in particular and the whole region in general, so that people in the region can travel anywhere. any route.

Comrade Le Tien Chau - Secretary of Hai Phong City Party Committee spoke at the meeting.
Speaking at the meeting, Mr. Le Tien Chau - Secretary of Hai Phong City Party Committee highly appreciated the efforts between the Project Management Board, Departments, branches and localities of the two sides that have come up with many solutions to overcome difficulties and remove obstacles to ensure the projects are implemented on schedule. Comrade Secretary of the Hai Phong City Party Committee said that together with Quang Ninh province, in recent times, Hai Phong city has also proactively built a bridge connecting with Hai Duong province. At the same time, the city is currently making concentrated efforts and determination to complete the coastal road project to make Hai Phong a driving force for development. According to the Secretary of the City Party Committee, this is also an internal need in the common development of the two localities, creating a driving force for development in accordance with the Regulations.of the Politburo. Comrade Secretary of the City Party Committee requested that in the coming time, agencies, units and localities of the two sides continue to cooperate closely and strive to complete the Project on schedule.