Vice Chairman of the City People's Committee Nguyen Duc Tho and functional agencies inspected the project on-site. (Haiphong.gov.vn) – On the afternoon of January 20, Vice Chairman of the City People's Committee Nguyen [...]


Vice Chairman of the City People's Committee Nguyen Duc Tho and functional agencies inspected the Project on-site.
(Haiphong.gov.vn) - On the afternoon of January 20, Vice Chairman of the City People's Committee Nguyen Duc Tho chaired an inspection of the progress of the investment project to renovate and upgrade National Highway 10 from Da Bac bridge to Kien bridge. Also attending were representatives of leaders of relevant departments, branches, localities and units.

Leaders of the Project Management Board reported at the inspection session.
According to the Investor's report, site clearance work for project construction involved 11 organizations and 1,564 households with a total area of more than 471,000 m2; Up to this point, Thuy Nguyen district has accounted for 100%, publicized the compensation plan, approved 545/1,564 households and made payments to 475 households. The remaining problem now is the residential land because there is no specific land price to calculate compensation and support for land recovery.

Taking advantage of favorable weather, construction units accelerated project progress.
Regarding construction work, up to now the contractor consortium has constructed 6.3km/10.9km on the right route and 4.9km/10.9km on the left route, reaching about 30% of the contract volume. Construction of bridges on the route such as Hang Luong bridge reached 40%; Price demand reached 53%; Trinh Xa bridge reached 66% of the contract volume; The two resettlement areas of Kien Bai and Luu Kiem have reached progress of 60% and 90% of the volume, respectively...
Emphasizing the meaning and importance of the Project, Vice Chairman of the People's Committee Nguyen Duc Tho said that, after 7 months of starting construction, the project has only been constructed on agricultural land and public land, the entire area related to more than 1,000 residential land households has not been implemented.

Vice Chairman of the People's Committee Nguyen Duc Tho delivered a concluding speech at the inspection of project implementation progress.
To ensure project progress, the Vice Chairman of the City People's Committee requested Thuy Nguyen district, the Project Management Board and the contractor to focus heavily on site clearance work on the basis of the approved land price; continue to accelerate the construction progress of resettlement areas; Review arising issues, and coordinate with relevant departments and branches to remove problems with premises and adjust projects...
The Vice Chairman requested contractors to focus on human resources and means to take advantage of time and favorable weather to speed up project progress. During the construction process, absolutely ensuring traffic safety and labor safety issues, striving to technically open the project to traffic in September this year.
Minh Hao – Dam Thanh