(Haiphong.gov.vn) - On the morning of December 24, Comrade Nguyen Van Tung, Deputy Secretary of the City Party Committee, Chairman of the City People's Committee inspected the construction progress and listened to the […]

(Haiphong.gov.vn) - On the morning of December 24, Comrade Nguyen Van Tung, Deputy Secretary of the City Party Committee, Chairman of the City People's Committee inspected the construction progress and listened to reports on compensation and site clearance of a number of key projects in Thuy Nguyen district. Attending the meeting were comrade Le Anh Quan, Permanent Vice Chairman of the City People's Committee; Nguyen Duc Tho, Vice Chairman of the City People's Committee and leaders of relevant departments and branches.

City People's Committee Chairman Nguyen Van Tung inspected the National Highway 10 renovation project
from Bac Stone bridge to Kien bridge
Regarding the project to build technical infrastructure in the North Cam River urban area, with a total area of 306.1 hectares recovered by 15 organizations and 2,785 households (residential land and land for housing is 1,300 households); Up to now, 7/15 organizations, 1,486/1,488 agricultural land households and 911/1,300 residential land households have received compensation and support. The actual area of site clearance that has been constructed is about 264.1 hectares, of which the City People's Committee has decided to hand over (phase 1) to the investor to implement the project of 220 hectares. In the coming time, we will focus on site clearance work, mobilizing to receive compensation, support and enforcement of land recovery in priority areas assigned by the city with a total of 67 households that have not received money in priority areas.

City People's Committee Chairman Nguyen Van Tung inspected the 359 Road Renovation and Upgrading Project
The project to renovate and upgrade National Highway 10 from Da Bac bridge to Kien bridge, site clearance work involves 11 organizations and 1,564 households with a total area of 471,173.8 m2. Currently, the People's Committee of Thuy Nguyen district has completed the inventory and publicized the compensation plan; Approved the compensation and support plan with a total cost of 65 billion VND, with 54 billion VND paid to households.

City People's Committee Chairman Nguyen Van Tung inspected the Minh Duc Town Road Improvement Investment Project
The project to renovate and upgrade Road 359 has 2 phases: Phase 1, from Tan Duong commune to the end of Trung Ha commune, has a total recovery area of 27.08 hectares with a route length of 8.05 km; 4 organizations and 1,727 households have had their land recovered. Up to now, 4 organizations and 1,690 households have approved the plan, 37 households have not approved the plan; 1,389/1,690 households have received compensation, 30/1,690 households have not received money. Phase 2, from Thuy Trieu commune to Tam Hung commune, has a total length of 5.2 km, an area of 15.6 hectares, with 1,101 households having their land recovered; To date, 1,067 households have approved the plan, 34 households have not approved the plan; 757 households received compensation, 310 households have not received money.

City People's Committee Chairman Nguyen Van Tung inspected the Minh Duc Town Road Improvement Investment Project
For the Minh Duc Town Road Improvement Investment Project, there are 6 organizations and 278 households with a total area of 70,379.5 m2, total route length of 2.7 km. Inventory has been conducted for 6 organizations and 278 households; Approved 278 households and 5/6 organizations; paid 237/278 households, 5/6 organizations; handed over 230 households and 5 organizations with an area of 66,747 m2. Up to now, there are 41 households that have not received compensation or support and 7 households have received money but have not handed over the premises.
City People's Committee Chairman Nguyen Van Tung spoke at the conclusion of the meeting
After inspecting the field and listening to reports, Chairman of the City People's Committee Nguyen Van Tung suggested that Thuy Nguyen district need to coordinate with relevant departments, branches, and units to focus on removing difficulties and obstacles to implement projects in the area. The Chairman of the City People's Committee also specifically directed a number of works related to projects in the district, which suggested: Project to renovate and upgrade National Highway 10 and Project to renovate and upgrade Road 359 must strive to be completed in 2022; Research on raising the height of Trinh Xa bridge in Thien Huong commune; The district researches and approves resettlement to suit the current time, adjusting to increase the residential land area in the resettlement project. With the Min Town Road Improvement Investment Projecth Duc and Trang Kenh 2 bridge strive to be completed before Lunar New Year 2022.
City People's Committee Chairman Nguyen Van Tung talks with people of Tan Duong commune
For Mang Nuoc street, the Chairman of the City People's Committee assigned Thuy Nguyen district to research and reduce the size of the road from the gate of the Navy Region 1 Command to Vsip industrial park; Studying and adjusting Ben Rung bridge and beltway 3. Regarding the investment project to build technical infrastructure in the new urban area North of Cam River, the Chairman of the City People's Committee assessed that the current site clearance progress is still slow and requested to urgently dismantle the works and structures of households who have received money and handed over the premises; Before the Lunar New Year, land must be recovered from households that have had enforcement decisions...
Hoang Tung – Dam Thanh