Standing Vice Chairman of the City People's Committee Le Anh Quan inspected land clearance work to recover land for the Project. (Haiphong.gov.vn) – On the morning of April 20, Vice Chairman [...]


Permanent Vice Chairman of the City People's Committee Le Anh Quan inspected land clearance work to recover land for the Project.
(Haiphong.gov.vn) - On the morning of April 20, Standing Vice Chairman of the City People's Committee Le Anh Quan chaired the inspection of implementation progress and listened to reports on the preparation of dossiers for enforcement of land recovery for the technical infrastructure construction investment project of North Song Cam New Urban Area, Thuy Nguyen district. Also attending were leaders of city and local departments and branches.

Permanent Vice Chairman of the City People's Committee Le Anh Quan inspects the construction work on site.
According to the report of the People's Committee of Thuy Nguyen district on the project site clearance compensation, the total area of land recovered is 306.1 hectares by 15 organizations and 2,788 households; Of which, residential land and land for housing are 1,300 households. To date, there are still 258 households in Tan Duong commune that have not yet handed over the premises, of which 82 households have approved the plan (of these, 47 households have completed enforcement documents and are currently transferring them to Departments and branches for consultation); 176 households have not approved the plan.

Permanent Vice Chairman of the City People's Committee Le Anh Quan concluded the meeting.
Through actual inspection and listening to reports at the meeting, Permanent Vice Chairman of the City People's Committee Le Anh Quan noted that Thuy Nguyen district has been drastic in site clearance work in recent times, however up to this point the site clearance progress to serve the Project is too slow. The Standing Vice Chairman requested the district to continue to focus heavily on propaganda work, mobilizing households to comply with the provisions of the law, urgently receive compensation, support and hand over the site for construction work, striving to hand over the entire project's clean site by June 2022. The Permanent Vice Chairman also expressed recognition that many households have actively and closely coordinated with local authorities and the Project Management Board in discussing solutions.ground pond, and at the same time hope that the people in the land clearance area agree with the city's policies, seriously comply with them, and the city will ensure maximum benefits for the people.

The Permanent Vice Chairman requested contractors to begin construction immediately after receiving clean premises.
Regarding construction work, the Permanent Vice President assigned the Project Management Board to coordinate closely with units under the Ministry of Construction to urgently make adjustments to the Project, along with urging contractors to prepare human resources, machinery and equipment to deploy construction immediately after receiving the site; Assign the city's functional branches to pay attention and support the district on procedures, mechanisms and policies...
Minh Hao; Photo – Dam Thanh