Vice Chairman of the City People's Committee Nguyen Duc Tho conducts a field inspection at the scene. (Haiphong.gov.vn) – On the afternoon of November 5, Vice Chairman of the City People's Committee Nguyen Duc Tho […]


Vice Chairman of the City People's Committee Nguyen Duc Tho conducts a field inspection at the scene.
(Haiphong.gov.vn) - On the afternoon of November 5, Vice Chairman of the City People's Committee Nguyen Duc Tho went on a field trip along the entire route to check the progress of the Project to renovate and upgrade National Highway 10, the section from Da Bac bridge to Kien bridge. Accompanied by leaders of relevant departments, branches and localities.

Leaders of the Urban Development and Civil Construction Investment Project Management Board spoke at the meeting.
According to the report of the Project Management Board, site clearance work for the project involves 11 organizations and 1,564 households with a total area of more than 471,173m2; At this point, the inventory work has been completed; Approved 545/1,564 households, paid for 475/1,564 households; handover area of 440,170.2m2 (reaching 93.4%). The biggest problem currently, in Kien Bai commune, from km 18 + 580 to km 18 + 700 on the right side of the route is still not eligible for construction due to ornamental plants and signs of Toan My Company Limited (HC Electronics Supermarket).

Currently, the construction volume of the route length reaches 41.94%.
Regarding the construction work, the renovation, upgrading and expansion of Highway 10 from Da Bac bridge to Kien bridge, the current construction volume of the route length reaches 41.94%. Regarding new bridge construction, Hang Luong Bridge's construction volume reached 38%; Construction volume price demand reached 35%; Trinh Xa bridge construction volume reached 42%...

Representative leaders of the Department of Transport spoke at the meeting.
To ensure completion of the Project's works on schedule, leaders of the Urban Development and Civil Construction Investment Project Management Board recommend that Thuy Nguyen district soon resolve problems for organizations within the area of the handed over ground to completely hand over to the construction unit, and come up with a compensation plan for households with residential land; At the same time, we asked the City People's Committee to agree to the policy of adjusting the detailed planning at a scale of 1/500 for resettlement areas in Luu Kiem commune, Kien Bai commune...

Vice Chairman of the City People's Committee Nguyen Duc Tho concluded the instructions at the meeting.
Through inspection and listening to reports at the meeting, Vice Chairman of the City People's Committee Nguyen Duc Tho emphasized that the project to renovate and upgrade Highway 10 from Da Bac bridge to Kien bridge is a key project of the city to develop traffic infrastructure, create inter-regional connections, the city always prioritizes resources for implementation. The Vice Chairman acknowledged the fierce participation of Thuy Nguyen district in site clearance work. Up to now, the public land and corridor land have been basically handed over and are being actively constructed by the contractor, this is a great effort.
Regarding site clearance work, the Vice Chairman assigned the Department of Natural Resources and Environment to preside with the Department of Finance to guide Thuy Nguyen district to determine specific land prices to calculate compensation, check, review, and appraise the quality of each dossier according to regulations. Thuy Nguyen district is assigned to continue propaganda work to mobilize people and organizations to soon agree to hand over the site to serve the project.
For construction work, the Vice President requested that from now until Tet, rough carpeting on the entire route must be completed; Regarding site problems in the HC Electronics Supermarket area, from now until November 10, 2021, construction must be carried out, and Thuy Nguyen district will be assigned to come up with a plan to protect the construction contractor.
The Vice Chairman also requested the Project Management Board, based on the handed over site, to request the construction contractor to concentrate human resources and equipment; Take advantage of favorable weather, work overtime, speed up construction progress to ensure project completion according to plan. During the construction process, it is necessary to ensure environmental hygiene, limit dust, have a sign system to ensure traffic safety for vehicles traveling on the route...
Minh Hao; Photo – Dam Thanh