– On the morning of October 5, Vice Chairman of the City People's Committee Le Khac Nam and leaders of a number of relevant departments, branches and localities inspected the progress of the […]

– On the morning of October 5, Vice Chairman of the City People's Committee Le Khac Nam and leaders of a number of related departments, branches and localities inspected the progress of the investment project to build new, renovate, upgrade and expand the capacity of social assistance facilities in Hai Phong city and the investment project to build Hai Phong College of Industry (phase 1).

City leaders inspect the project at Thanh Xuan School of Social Labor.
The investment project to build, renovate, upgrade, expand to improve the capacity of social assistance facilities in Hai Phong city includes 2 items implemented at Thanh Xuan School of Social Labor (Thanh To ward, Hai An district) and Mental Health Nursing Center (Dung Tien commune, Vinh Bao district), with a total investment of more than 98.2 billion VND from the central and city budgets.

Inspect the construction at the Mental Health Nursing Center.
Up to this point, the project at Thanh Xuan School of Social Labor has completed construction of the cafeteria area; Completing a row of shelters and homes for children infected with HIV/AIDS; Completed construction of technical infrastructure of 5 shelters; Construction of the transformer station, boundary walls, drainage system is underway... The project at the Mental Health Nursing Center has completed the rough construction and is completing the patient housing (block D); self-managed patient home (block A); fire pump station; wastewater treatment system; Currently constructing wastewater collection system, gates, walls, signs...

Inspecting the project at Hai Phong Industrial College.
The Hai Phong Industrial College construction investment project (phase 1) is implemented on an area of about 7.4 hectares, with a total investment of nearly 375.7 billion VND from the city budget. The project will be implemented from 2021 - 2024, including synchronous construction items that meet the standards of a high-quality vocational college, with an enrollment scale of about 2,000 students/trainees/year. Including the administrative building, lecture hall, basic science building, information technology and pedagogy department, economics department, electrical and electronics department, mechanical engineering department, automobile technology department, construction department, dormitory and cafeteria, library, conference hall... Up to now, the project is actively being constructed, reaching about 50% of the contract value, basically meeting the schedule.

Vice Chairman of the City People's Committee Le Khac Nam spoke concluding the inspection.
Through actual inspection of the projects, Vice Chairman of the City People's Committee Le Khac Nam emphasized that these are important projects for the city, partly demonstrating profound humanity, partly playing the role of training high-quality human resources to meet the needs of industrialization and modernization of the city. Vice Chairman of the City People's Committee acknowledged and praised the Project Management Board, contractors, and related units for closely coordinating and implementing the project promptly and seriously, initially ensuring quality as required.

Inspecting the project at Thanh Xuan School of Social Labor.
To achieve the goal of completing the investment project to build, renovate, upgrade and expand the capacity of social assistance facilities in Hai Phong city in December 2023; Completing the Hai Phong Industrial College Construction Investment Project (phase 1) in May 2024, the Vice Chairman requested the Project Management Board and contractors to build a progress chart, concentrate human and material resources; Ensure proper construction of design, technical and aesthetic documents of projects.

The project at the Mental Health Nursing Center is being actively constructed by the contractor.
For projects at Thanh Xuan School of Social Labor and Mental Health Nursing Center, it is necessary to learn from the process of designing electricity and water to pay attention to the appropriate usage needs of each project beneficiary (addicts, mentally ill people...). During construction, it is necessary to make appropriate repairs to avoid unfortunate events occurring during use. There should be signs, barriers, and training for workers to ensure labor hygiene and safety. Accelerate progress and promptly disburse centrally allocated capital.

Construction progress of Hai Phong College of Industry is estimated to reach about 50% of the contract value, basically meeting the schedule.
Regarding the Hai Phong Industrial College project, the city currently has a policy to expand the road in front of the school gate. In this regard, the Vice Chairman of the City People's Committee assigned the Department of Transport to coordinate with An Lao district to urgently carry out construction investment procedures before the inauguration of the Hai Phong Industrial College project, to avoid congestion and ensure traffic safety for teachers and students of the school.