(Haiphong.gov.vn) - On the afternoon of June 4, Mr. Nguyen Duc Tho, Vice Chairman of the City People's Committee, inspected the progress of the Dinh Bridge Construction Investment Project [...]

(Haiphong.gov.vn) - On the afternoon of June 4, Mr. Nguyen Duc Tho, Vice Chairman of the City People's Committee, inspected the progress of the Dinh Bridge Construction Investment Project in An Son Commune, Thuy Nguyen District and the Quang Thanh Bridge Initial Construction Project in Quang Hung Commune, An Lao District. Accompanied by leaders of relevant departments, branches and localities.

Vice Chairman of the City People's Committee Nguyen Duc Tho inspected the construction progress at Dinh Bridge

The road leading to Hai Duong province at Dinh bridge is being completed
According to the report of the Hai Phong Traffic Construction Investment Project Management Board, the Dinh Bridge Construction Investment Project (connecting An Son commune, Thuy Nguyen district with Kinh Mon town, Hai Duong province), has so far reached about 95% completion. As for the bridge, the entire lower structure, upper structure, asphalt concrete spread on the bridge deck, lighting system, railings and bridge load testing have been completed; The remaining work is to install expansion joints (2/4 joints have been completed), and paint road markings. The road leading to Hai Duong has completed the roadbed structural layers and will continue to complete the class 1 gravel layer, asphalt concrete, install traffic safety signs, lighting, and road markings. The path towards Hai Phong has completed its structural layerThe road base will continue to complete the class 1 gravel layer, asphalt concrete, install traffic safety signs, lighting, and road markings.

Quang Thanh Bridge on Hai Phong city side is continuing to be completed
For the investment project to build Quang Thanh bridge (connecting Quang Hung commune, An Lao district with Thanh Ha district, Hai Duong province), to date the completion volume has reached about 97%. Regarding the bridge, the entire lower structure and upper structure have been completed, asphalt concrete is spread on the bridge deck, expansion joints are installed, lighting systems, railings and bridge load testing are completed; The remaining work is painting road markings. The approach road and dike bypass road on Hai Duong side have completed the entire road base structure, asphalt concrete has been spread on the road surface and corrugated iron has been installed. The path and retaining wall on the Hai Phong side have been constructed at about 90% of the volume; The remaining work is to construct 2 layers of gravel aggregate for the road surface, spread asphalt concrete and paint road markings. The Hai Phong side access road has been completedOperate the entire ground structure and road foundation; The remaining work is spreading asphalt concrete and painting road markings.

Vice Chairman of the City People's Committee Nguyen Duc Tho inspected progress at Quang Thanh Bridge
Through the actual inspection and listening to the report, Vice Chairman of the City People's Committee Nguyen Duc Tho acknowledged and appreciated the efforts of the Management Board of Construction Investment Projects of Hai Phong traffic works and localities, despite many difficulties, still ensuring the set progress. At the same time, it is recommended that the Management Board complete relevant legal procedures for inspection by the Ministry of Transport before inaugurating the two bridges. Vice Chairman of the City People's Committee requested that Thuy Nguyen and An Lao districts need to take measures to ensure traffic safety during the bridge completion period and take measures to strictly control people traveling between localities to ensure the prevention and control of COVID-19 epidemic; Along with that, prepare the ground to hold the inauguration ceremony of the bridges.
Phuong Trang