At around 4:00 p.m. on May 18, the 110 KV line route 178 E2.1-172 E2.13-172 E2.33 suffered a prolonged problem. After inspecting the entire line, the Management Team [...]


Accordingly, in the process of hoisting ornamental trees, the car driver violated the safe distance and discharged electricity to the 110KV line, causing the top of the tree to get entangled in the power line, fraying and breaking the entire aluminum wire, not ensuring operating conditions, causing a power outage at 4 110KV stations Trang Due, LGD, An Lao, Tien Lang.

This is a serious incident, affecting the supply of electricity to industrial zones and people's lives. Immediately after receiving the news, the Electricity Company mobilized its forces to make a record, review and quickly handle the incident. By 5:00 p.m. the same day, the repair was completed and power was restored to serve customers.
The incident occurred, once again showing the need to further raise people's awareness in ensuring power grid safety and the need to strictly handle violations. The Electricity Company also requested local authorities to consider and dismantle construction works that violate power grid safety corridors.
Vu Duyen
thanhphohaiphong.gov.vn