Standing Vice Chairman of the City People's Committee Nguyen Xuan Binh and leaders of functional branches inspected the field at the project construction site. (Haiphong.gov.vn) […]


Permanent Vice Chairman of the City People's Committee Nguyen Xuan Binh and leaders of functional agencies inspected the field at the project construction site.
(Haiphong.gov.vn) - On the afternoon of October 29, Standing Vice Chairman of the City People's Committee Nguyen Xuan Binh inspected the progress of the implementation of the investment project to build a road connecting Nam Cau Binh intersection to the intersection of Ton Duc Thang street - Mang Nuoc street. Accompanied by representatives of leaders of relevant departments, branches and units.
According to the report of the Hai Phong Traffic Construction Investment Project Management Board, regarding site clearance work, up to now, An Duong district has approved compensation and support plans for 77 households with a total compensation cost of nearly 13,776 billion VND. Currently, 76/77 households have received compensation and support (01 household has not received compensation due to the recommendation of a low compensation unit price); The district has handed over to the Project 30,178.50 m2 of agricultural land used by people and in-field ditch land managed by the commune; Regarding the residential land portion of 46 households with an area corresponding to more than 2,128m2, the inventory has now been completed, the District Compensation Council has hired a Land Price Appraisal Consulting unit to develop a specific land price...

Contractors are actively constructing within the area of the handed over site.
Regarding the construction work, within the area of the handed over site, the contractors have been actively implementing the construction work, so far a number of main workloads have been carried out such as: clearing the site of 36,500 m2; organic excavation and peeling of roadbed 48,200 m3; foundation 38,000m3; Drilling soil cement piles resulted in 1,962/2,083 piles; Completed construction of 02 culvert sections L=45.6m and is constructing the next 02 culvert sections; Completed the erection of 2 temporary L20 centrifugal double column poles and pulled and installed the line to serve moving the 110kV power line...
Through field inspection at the scene and listening to reports from relevant sectors and units, Standing Vice Chairman of the City People's Committee Nguyen Xuan Binh welcomed the efforts of An Duong district, the Project Management Board and related sectors who have been very active in site clearance work, approving compensation plans to support speeding up the handover of the site for the project, mobilizing equipment, vehicles, and human resources to organize construction to strive. In December 2020, the route will open to Road 208. The Vice Chairman acknowledged and appreciated Vilaco Joint Stock Company for supporting the city's policy, proactively adjusting production activities, coordinating with An Duong district to hand over the Company's area to the contractor to serve the project's construction.
The Vice Chairman also reminded that during the construction process, contractors need to pay attention to the power lines above and proactively take measures to absolutely ensure labor safety at the construction site. Regarding disbursement of public investment capital, the Project Management Board coordinated with relevant Departments and branches to propose a policy of prioritizing capital allocation for the project.