On the afternoon of April 27, the City People's Committee met to hear a report on the implementation of the DEEP Industrial Park infrastructure investment and business project [...]

Comrade Tran Luu Quang, Member of the Party Central Committee, Secretary of the City Party Committee attended and directed the meeting; Comrade Nguyen Van Tung, Deputy Secretary of the City Party Committee, Chairman of the City People's Committee chaired the meeting. Also attending were leaders of relevant departments, branches, localities and units.
According to the Hai Phong Economic Zone Management Board, currently, industrial parks in the Dinh Vu area have basically completed site clearance, are implementing construction investment and attracting investment; Only Hai Phong DEEP C3 International Gateway Port Industrial Park has land problems. Of the total land area of the project is 526.81 hectares, currently 327.8 hectares have been handed over, mostly water surface land outside the dyke, the rest are lakes, salt fields interspersed with land areas that have not yet been cleared. It is expected that by the end of 2022, site clearance of lots CN1, CN2, CN3, CN4 will be completed to qualify for infrastructure development and investment attraction.

Report on the implementation status of DEEP C1 Industrial Park investment and construction projects; DEEP C2A; DEEP C2B, DEEP C3; implementation status of the Non-Tariff Area and Nam Dinh Vu Industrial Park; implementation status of the investment project to build the Nam Dinh Vu sea dyke... Business leaders all expressed their determination to speed up the construction progress of industrial parks, and at the same time hoped that the city would pay attention and resolve difficulties and obstacles that are affecting the progress of projects.
Typically, the difficulties and obstacles affected by the 1/2000 Scale Planning and 1/500 Scale Planning approved by the City People's Committee in the area of Industrial Park infrastructure investment projects in the Dinh Vu and Cat Hai area have some contents that are different from the General Planning for construction of Dinh Vu - Cat Hai Economic Zone, but have been built and attracted investment by investors. fourth.
DEEP C proposed that the city adjust the criteria for industrial park land use (from 60% to 70%) according to National Standards on Construction Planning, in accordance with new construction and production technologies; early clearance of DEEP C 3 Industrial Park; Proposal to build a road connecting the coastal road with Dinh Vu area through DEEP C2 Industrial Park; Plan to retain, renovate and embellish Cat Hai town into an ecological service urban area, connected and symbiotic with DEEP C3 industrial park. Along with that, it is proposed to close Dinh Vu landfill in 2023 and allow DEEP C to conduct research on the solar energy development project; DEEP C also proposed that the city consider stopping the expansion of DAP's Gyps landfill as soon as possible and make a treatment plan.The impact of landfills on the city environment.
On behalf of Sao Do Group Joint Stock Company, we propose that the city urgently implement investment procedures for the Nam Dinh Vu sea dyke project and hope that the city will clear the land of illegal clam farming households in the 3,000 ha area south of Nam Trieu gate, besides creating conditions for Sao Do Group Joint Stock Company and other businesses to exploit sand mines to ensure project implementation progress; At the same time, it is proposed to build the main road of Dinh Vu peninsula, connecting with Tan Vu - Lach Huyen road...
Emphasizing the direction at the meeting, City Party Secretary Tran Luu Quang affirmed the important significance of investing in building infrastructure of industrial parks in this area. According to the Secretary of the City Party Committee, accelerating the construction progress of industrial parks is a big and quite urgent issue to ensure there is a clean land fund to attract investment, meet the requirements and goals of attracting FDI capital as well as mobilizing social investment capital, contributing to realizing the city's development aspirations. Comrade Secretary of the City Party Committee assigned the City People's Committee to urgently research and directly resolve each issue proposed by businesses, quickly remove difficulties and obstacles to speed up the progress of infrastructure construction of industrial parks in the Dinh Vu-Cat Hai area.

Regarding the business's recommendations at the meeting, Chairman of the City People's Committee Nguyen Van Tung said that for recommendations on Planning, the city will wait for the Prime Minister to approve the General Planning and continue to process and resolve.
The Chairman agreed with the proposal to increase the industrial land fund from 60% to 70%, assigning the proposed industries to implement. Expressing agreement with the proposal to retain Cat Hai town, the Chairman noted that there needs to be more convincing grounds. The Chairman assigned the Department of Agriculture and Rural Development to consult the Ministry of Agriculture and Rural Development to resolve DEEP C's proposal to convert 8.5 hectares of forest. Regarding the recommendations about Dinh Vu landfill and resolving Gyp DAP landfill, the Chairman said that the city has a suitable solution. Regarding resettlement arrangements for households in Cat Hai town, the Chairman said that first of all, 120 households in Doai village, Dong Bai commune will be provided; The remaining number will continue to be resolved in the near future; relocation of martyrs cemetery in Cat Haiwill continue to do so. Currently, the city also has plans to move fish sauce production facilities in Cat Hai; At the same time, focus on directing and speeding up the construction progress of the new tourist port... Agreeing on the need to build a road connecting the industrial park with the coastal road, however, according to the Chairman, there needs to be time to research and allocate resources. The Chairman of the City People's Committee also asked the sectors to continue to research and propose the most suitable plan to accelerate the construction of the Nam Dinh Vu sea dyke.
Minh Hao