On the morning of March 11, comrade Le Trung Kien, Member of the Standing Committee of the City Party Committee, Vice Chairman of the City People's Committee chaired a meeting with sectors and functional units [...]

On the morning of March 11, Comrade Le Trung Kien, Member of the Standing Committee of the City Party Committee, Vice Chairman of the City People's Committee chaired a meeting with relevant sectors, functional units and localities to listen to reports on the progress of site clearance for construction investment projects in the city in the first quarter of 2026 and plans to build resettlement areas to serve the implementation of projects in the near future.

According to a report from the Department of Agriculture and Environment, in 2026, the city will carry out site clearance work for 431 projects with a total recovery area of more than 14,942 hectares, involving over 165,600 households and 424 organizations. In the first quarter of 2026, there are 53 projects in 32 localities committed to completing site clearance, with an area of more than 577 hectares. To date, the implementation volume has reached about 80% in terms of area and number of households. Of these, 33 projects in 21 localities were basically completed on schedule; The remaining 20 projects are at risk of not completing the first quarter plan. The main reason is that some households have not agreed on the compensation price, requested resettlement despite not meeting the conditions, or encountered difficulties in determining land users due to handwritten purchases and lack of legal documents.
For resettlement work, the review shows that the whole city has 163 projects that need to arrange resettlement for nearly 13,000 households. Currently, 46 projects do not meet enough demand, of which 27 projects propose to build new resettlement areas and 19 projects propose to expand existing areas.

By listening to reports from departments, branches and localities, Vice Chairman of the City People's Committee Le Trung Kien acknowledged and praised the efforts of localities and relevant agencies in overcoming difficulties, doing a good job of site clearance and resettlement projects. Especially units with large clearance volumes. Besides the results achieved, the results of disbursement of public investment capital and site clearance work in the first quarter still did not meet the requirements compared to the proposed scenario.
To complete the 2026 plan goals, especially in site clearance and resettlement arrangements, the Vice Chairman emphasized that the entire city needs to agree on a common policy, be highly focused, and accelerate site clearance progress to achieve the highest results. This is not only an economic task but also a political responsibility to the Party Committee and people of the city, to create a solid foundation for the sustainable development of Hai Phong in the coming period. All levels, sectors and localities thoroughly grasp the spirit of determining that land clearance work is an imperative and require close coordination in implementation. Departments and branches must develop detailed site clearance and disbursement plans each quarter as a basis for monitoring, reviewing and comparing implementation results.

City leaders recommend that localities, especially units that are behind schedule compared to their first quarter commitments, must be highly focused and drastic in implementation and removing difficulties; Clearly classify each problem case to take advocacy or enforcement measures according to regulations, and do not let the delay in site clearance affect the progress of disbursement of public investment capital.

Regarding resettlement, the Department of Construction presides and coordinates with relevant units to urgently establish a project to build resettlement areas throughout the city with the motto of "resettlement must be one step ahead, ensuring people have a new place to live that is equal to or better than the old place to quickly hand over the site to the project." Localities need to base on the city's general socio-economic planning to build and propose resettlement plans with a long-term vision. In particular, the resettlement area must have synchronous infrastructure, beautiful landscape, and ensure living conditions equal to or better than the old place of residence. The Department of Construction reviews construction standards guidelines and soon synthesizes and reports to the city according to regulations.

The Department of Finance closely follows the actual progress to update and adjust the growth scenario and disbursement scenario closely to the implementation situation, as a basis for control and direction. Project Management Boards proactively coordinate with localities to quickly approve resettlement projects. For approved plans, funds must be transferred promptly so that localities can pay people.
The Department of Science and Technology needs to continue to perfect and effectively operate land clearance management software to ensure openness, transparency and help city leaders closely monitor the implementation progress of each locality./.