Vice Chairman of the City People's Committee Nguyen Duc Tho inspected site clearance work to serve the project. (Haiphong.gov.vn) – “Localities need to drastically and urgently resolve [...]


Vice Chairman of the City People's Committee Nguyen Duc Tho inspected site clearance work to serve the project.
(Haiphong.gov.vn) - "Localities need to drastically remove and urgently resolve obstacles and existing problems in site clearance work to ensure the overall progress of the entire project..." Vice Chairman of the City People's Committee Nguyen Duc Tho gave such instructions when going on a field trip to the entire route to check the progress of the investment project to build a road connecting Lang Am bridge, Ly Hoc commune, Vinh Bao district to the coastal road, in the afternoon. May 20. Accompanied by representatives of relevant departments, branches, localities and units.

Inspect construction work.
According to the report of the Hai Phong Traffic Construction Investment Project Management Board, regarding site clearance work in Vinh Bao district, the project goes through 5 communes, recovering about 19.9 hectares, involving 700 households and 5 organizations. To date, the district has approved plans for 655 households (84 more households have approved plans compared to the time of inspection on March 15, 2022); Of which, 611 households have received money (95 more households have received money compared to March 15, 2022); 611 households have handed over premises (225 more households handed over premises compared to March 15, 2022).

Leaders of the Project Management Board investing in construction of Hai Phong traffic works reported at the meeting.
In Tien Lang district, the project goes through 2 communes, reclaiming about 9.1 hectares, involving 61 households and 1 organization. To date, the district has approved the plan for 57 households, of which 46 households have received money (35 more households received money compared to March 15, 2022); 19 households have handed over the premises (15 more households handed over the premises compared to March 15, 2022).

Contractors are focusing on human resources and means to speed up progress.
Currently, the contractor consortium is organizing simultaneously, including: construction of the package from Lang Am bridge to the end of the bridge over the Chanh Duong river and the 1.36km section on the left side of the Chanh Duong river, with an estimated value of 40.2% of the contract; The bidding package for the construction of a bridge over the Thai Binh river and access roads at both ends of the bridge, the completed volume has reached more than 25% of the contract. To ensure project construction progress, the Project Management Board requests that Vinh Bao district continue to approve the compensation and support plan for the remaining households in May under the direction of the City People's Committee; Tien Lang district will soon approve additional plans according to other support mechanisms, propagate and mobilize households to hand over the premises.

Vice Chairman of the City People's Committee Nguyen Duc Tho spoke concluding the inspection.
Through inspection, Vice Chairman of the City People's Committee Nguyen Duc Tho assessed that site clearance work in localities had changed compared to the previous inspection, however, it still did not meet the requirements. The Vice Chairman requested local authorities to focus heavily on propaganda work, speed up site clearance progress, and urgently move power projects on the route.
Regarding resettlement work, the Vice Chairman requested localities to review and develop specific plans; The Project Management Board coordinates with local authorities in site clearance work and estimates capital plans for the project; Urges contractors to continue focusing on human resources and means to speed up progress, ensuring connectivity and overall progress of the entire project with the goal of opening the route on September 2 this year.
The Vice President also assigned relevant departments and branches to coordinate and support localities in resolving problems in site clearance and project construction. At the same time, note that during the construction process, labor safety and traffic safety on the route must be absolutely guaranteed.
Minh Hao; Photo – Dam Thanh