On October 11, 2023, the People's Committee of Hai Phong city issued Decision No. 3178/QD-UBND on the decision to approve the investment policy of the […]

On October 11, 2023, the People's Committee of Hai Phong City issued Decision No. 3178/QD-UBND on Decision approving the investment policy of the land use rights auction project to invest in the construction of a new urban area along Do Muoi extended street and the area. neighborhoods in communes: Tan Duong and Duong Quan, Thuy Nguyen district with some main contents as follows:
1. Form of investor selection: Auction of land use rights to select investors to implement investment projects according to the provisions of land law.
2. Project goals:
Organize auctions of land use rights, build new urban areas, contribute to urban embellishment, socio-economic development of communes: Tan Duong, Duong Quan, Thuy Nguyen district in particular and the city in general. Bringing state budget revenue from auctioning land use rights to implement projects, creating jobs for workers in the district.
Implement urban beautification and synchronous urban development of new city center infrastructure according to planning orientation. Create a premise for socio-economic development, security and defense in the region. At the same time, contributing to the successful implementation of Resolution No. 12/NQ-HD dated July 29, 2020 of the XXV Thuy Nguyen District People's Council for the 2020-2025 term.
3. Project scale:
Total land area expected to be used: 493,665.41 m2.
Products and services provided: all types of low-rise housing, apartment buildings, public works, commercial and service works, schools and synchronous technical infrastructure works.
Construction architectural scale:
– Roughly completing the exterior of the adjacent housing area with a total land area of about: 100,771.2 m2, total number of land lots is about 1,146 lots with a maximum height of 05 floors, construction density from 78% to 100% in 39 adjacent land plots including from N1 to N32, LK5, LK6, LK11, LK12, LK12A, LK14, LK15.
>
– Construction of a social housing area (apartment) with a land area of about 34,239.5 m2 in 04 plots of land including NXH1, NXH2, NOXH1, NOXH2 with a maximum height of 04 to 05 floors, the total number of apartments is about 510 units. Maximum construction density ranges from 55% to 75%.
>
– Construction of public land for residential units with an area of about 2,303.4 m2, including 02 plots of land CC1 and CC2, maximum construction density of 40%, maximum height of 03 floors.
– Construction of educational land on 04 plots of land from GD1 to GD4 with an area of about 24,366 m2, maximum height of 03 floors, maximum construction density of 40%.
– Construction of green trees and public water surface with a total land area of about 92,181.81 m2.
– Construction of technical land with an area of about 10,116.17 m2.
– Construction of a public parking lot with an area of about 1,198.8 m2.
– Traffic construction has an area of about 202,718.53 m2 (In which internal roads have an area of about 192,318.72m2, the area of Do Muoi street passing through the project is about 10,399.81 m2).
4. Total expected investment capital: 10,157.9 billion VND (Ten thousand, one hundred fifty-seven billion, nine hundred million VND).
5. Operational term of the project: 50 years, from the date of issuance of the Decision on winning the auction of land use rights to implement the project.
6. Project implementation location: The project's land area is located in communes: Tan Duong, Duong Quan, Thuy Nguyen district, Hai Phong city.
7. Project implementation progress:
Progress of basic construction and putting the project into operation or exploitation: 07 years from the date of issuance of the Decision on winning the auction of land use rights to implement the project.
8. Incentives, investment support and applicable conditions:Projects enjoy incentives according to current legal regulations.