Inspection at the construction site of Quang Thanh Bridge Project. (Haiphong.gov.vn) – Do not let the delay in handing over the site affect the overall progress of [...]


Inspection at the construction site of the Quang Thanh Bridge Project.
(Haiphong.gov.vn) - Not to let the delay in handing over the site affect the overall progress of the project, Permanent Vice Chairman of the City People's Committee Nguyen Xuan Binh emphasized such instructions at a field trip to check the progress of the construction investment projects of Quang Thanh bridge and Dinh bridge, on the afternoon of July 7. Accompanied by representatives of leaders of relevant departments, branches and localities; Representatives of the People's Committee of Thanh Ha district, Kinh Mon district (Hai Duong province).
Through inspection at the construction site of the projects, Standing Vice Chairman of the City People's Committee Nguyen Xuan Binh recognized and highly appreciated the Project Management Board and the contractors. After only 2 months of starting construction, they have actively deployed all parts of the work, such as: completing the setup of the field laboratory, the grid marker system for construction, mobilizing the floating system and bored pile construction equipment system, setting up the signaling system to ensure waterways...
For the Quang Thanh Bridge Project, the Permanent Vice Chairman expressed his thanks to Thanh Ha district, Hai Duong province for quickly handing over enough land to the contractor to serve the construction. On the bank of An Lao - Hai Phong, currently the An Lao District People's Committee has just finished inventorying 04 households outside the dyke, 31 households inside the dyke and is evaluating the origin of the land. The Vice Chairman requested An Lao district leaders to directly pay attention to directing site clearance work to ensure the actual handover of the site.

Inspection at the Dinh Bridge Project construction site.
For the Dinh Bridge Project, the Standing Vice Chairman applauded Thuy Nguyen district for doing a good job in site clearance work. Up to this point, the district has approved the compensation and support plan for 75 agricultural land households with an amount of nearly 8.8 billion VND. The Vice Chairman suggested that Thuy Nguyen district continue to coordinate closely with Kinh Mon district, Hai Duong province in site clearance work to ensure the progress of the two bridge projects, not letting the reason for slow site clearance affect the overall construction progress.
Regarding the funding source for the two projects, the Vice Chairman requested the Department of Finance and the Department of Finance to coordinate with the Management Board to balance and supplement capital sources to ensure progress for the projects. At the same time, please note that the Project Management Board and contractors must comply and absolutely ensure labor safety issues during the construction process of projects.

At the Dinh bridge construction site, the contractor has mobilized a system of equipment to construct bored piles and steel sheet piles.
*The Quang Thanh bridge construction investment project has the scale of building a new permanent bridge made of reinforced concrete and prestressed reinforced concrete across the Van Uc river and the path at both ends of the bridge according to class III plain road standards. The construction site is located in An Lao district, Hai Phong city and Thanh Ha district, Hai Duong province.
*The investment project to build Dinh Bridge has the scale of building a new permanent bridge made of reinforced concrete and prestressed reinforced concrete to cross the Han - Cam river and access roads at both ends of the bridge according to class III plain road standards. The construction site is located in Thuy Nguyen district, Hai Phong city and Kinh Mon town, Hai Duong province.
Minh Hao