Vice Chairman of the City People's Committee Nguyen Duc Tho inspected the site. (Haiphong.gov.vn) – On the afternoon of April 6, Vice Chairman of the City People's Committee Nguyen Duc Tho […]


Vice Chairman of the City People's Committee Nguyen Duc Tho inspected the field.
(Haiphong.gov.vn) - On the afternoon of April 6, Vice Chairman of the City People's Committee Nguyen Duc Tho on-site inspected the progress of the investment project to build a road connecting the Nam Cau Binh intersection to the intersection of Ton Duc Thang street - Mang Nuoc. Accompanied by leaders of relevant departments, branches, localities and units.
According to the report of the Traffic Construction Investment Project Management Board, the site clearance work of the road connecting the Southern Bridge Binh intersection to Mang Nuoc road involves 7 organizations and 109 households with a total area of nearly 75,732 m2, 53,030 m2 has been handed over (reaching 70%), so according to the assessment, the progress of site clearance work is very slow compared to plan. proposed.
Regarding construction work, the contractor has currently been drilling soil cement piles; D1000, D800, D400, D300 drainage systems, box culverts, technical trenches; Excavation and embankment of the road base, gravel grading, layer 1 asphalt concrete covering a length of 800m from the intersection of South Cau Binh to Road 208... the contractor's construction volume is estimated at 54% of the contract value.

The site clearance work to serve the project is currently very slow compared to the plan. (Photo: Nguyen Hong Phong).
Through field inspection and listening to reports from sectors and localities, Vice Chairman of the City People's Committee Nguyen Duc Tho emphasized that the route connecting the intersection of Nam Cau Binh to the intersection of Ton Duc Thang - Water Trough is an important traffic project that will contribute to reducing congestion and the risk of traffic accidents. The project has been identified by the city as a key project and fully allocated resources for implementation.
Regarding the existing problems in site clearance work, Vice Chairman Nguyen Duc Tho requested An Duong district to focus on reviewing the origin of land, making plans for compensation and support for residential land, ensuring full settlement of policies and regimes for people in accordance with the law. The Vice Chairman requested the district to proactively coordinate and work with city authorities to complete site clearance work, and at the same time strengthen propaganda and advocacy for people and organizations to strive to hand over the entire remaining site to construction contractors by April 15, 2021 to ensure the overall progress of the project. The Vice Chairman also requested construction units to focus on human resources, equipment, and technical means to urgently speed up construction.Project implementation progress, during the construction process, it is necessary to absolutely ensure labor safety and traffic safety issues, have measures to fence the construction site area, organize traffic flow...
| According to the Project Management Board's expected progress for Section Km0+800 – Ton Duc Thang 4 intersection – Water Trough – NH.5:
May 15, 2021: completed drainage system and technical trench; May 31, 2021: completed construction of road base and road surface; June 15, 2021: complete lighting system, sidewalks, trees and traffic safety throughout the route. |
Minh Hao