(Haiphong.gov.vn) - On the afternoon of February 19, Mr. Nguyen Xuan Binh, Standing Vice Chairman of the City People's Committee - Chairman of the Appraisal Council chaired the meeting of the Council [...]

(Haiphong.gov.vn) - On the afternoon of February 19, Mr. Nguyen Xuan Binh, Standing Vice Chairman of the City People's Committee - Chairman of the Appraisal Council chaired the meeting of the Appraisal Council of the Pre-Feasibility Study Report of the Investment and Construction Project of the North Song Cam New Urban Area (Phase 1).
Overall perspective of the Project model.The investment project to build architectural works in North Song Cam New Urban Area (Phase 1) is invested by the Urban Development Project Management and Civil Construction Investment Board, located within the boundaries of Tan Duong and Duong Quan communes, Thuy Nguyen district, with a total expected investment of nearly VND 9,300 billion.
The project includes the following items: construction of an Administrative and Political Center with a scale of 2 basements and 9 floors above...; Build a Square with a system of fountains, monuments, trees, lawns... on an area of nearly 19 hectares; Static parking; 22kv medium voltage electrical system, RMU distribution station for architectural works and lighting electrical systems; Build a Monument to President Ho Chi Minh on an area of about 1000m2.
After listening to the Investor present the report and seriously and objectively discussing it, the Appraisal Council members basically agreed with the Pre-Feasibility Study Report of the Investment and Construction Project of Architectural Works in North Cam River New Urban Area (phase 1).
Permanent Vice Chairman of the City People's Committee Nguyen Xuan Binh emphasized that the project will be an important breakthrough in expanding urban development into city to the north.Speaking at the conclusion of the meeting, Permanent Vice Chairman of the City People's Committee Nguyen Xuan Binh emphasized that the project has a particularly important significance in implementing Resolution No. 45 of the Politburo, striving to complete the move of the city's administrative center to the North of the Cam River by 2025, creating a breakthrough in urban development to expand the city to the North, contributing to promoting economic development. social economy of the city.
The Permanent Vice Chairman assessed that the project's pre-feasibility study report is basically in line with the roadmap for implementing Resolution 45 of the Politburo; the city's action programs, Resolutions and Implementation Plans; consistent with general planning, land use plans and land use purposes; fully meets the conditions of environmental impact, ensures national defense and security requirements, functions according to the criteria of the law on city administrative and political centers... meets the requirements for a working headquarters to serve the long-term development of the city in the future.
The Permanent Vice Chairman requested the Urban Development Project Management and Civil Construction Investment Board to receive comments from Council members based on the provisions of law, the policy of building and developing new urban areas and administrative centers, and the state's economic and technical regulations, to urgently complete the report to submit to the city's competent agencies for consideration and development. declare.
Minh Hao