Vice Chairman of the City People's Committee Nguyen Duc Tho chaired the meeting with relevant functional branches and units. (Haiphong.gov.vn) – On the afternoon of December 1, Vice Chairman […]


Vice Chairman of the City People's Committee Nguyen Duc Tho chaired the meeting with relevant functional branches and units.
(Haiphong.gov.vn) - On the afternoon of December 1, Vice Chairman of the City People's Committee Nguyen Duc Tho chaired a meeting with leaders of relevant departments, branches and units to hear progress reports on the implementation of the investment project to build container terminals No. 3 and 4 of Hai Phong International Gateway Port (at Lach Huyen Port Area).
The project of 2 container berths No. 3 and 4 has an investment and construction scale of 750m in length (375m/1 berth); receive container ships of 100,000 DWT; Build a barge wharf to receive ships and barges with a capacity of 100-160 TEU; Invest in technical infrastructure projects and synchronous equipment to meet the throughput of 1.0 - 1.1 million TEU/year.
Leaders of Hai Phong Port Joint Stock Company said that after the Prime Minister approved the investment policy in Decision No. 1323/QD-TTg dated October 9, 2019, Hai Phong Port has now completed the outline and cost estimate of the investment preparation step; Complete topographic and geological surveys; berth route agreement at the Maritime Administration; Complete the task of detailed construction planning at 1/500 scale...

Connecting road traffic to Container Terminal No. 3 and 4.
Emphasizing his speech at the meeting, Vice Chairman of the City People's Committee Nguyen Duc Tho affirmed that the Resolution of the 16th City Party Congress set a target that by 2025, the output of goods through the ports should strive to reach over 300 million tons, so the city always identifies the development of seaport services as an important goal. To speed up the progress of project implementation, Vice Chairman Nguyen Duc Tho requested Cat Hai district to urgently coordinate with the Department of Construction to soon approve the detailed planning project at 1/500 scale, completed before December 7, 2020; The Department of Natural Resources and Environment was assigned to guide Hai Phong Port on procedures related to land allocation and land lease for project implementation. Regarding technical infrastructure serving the project, Deputy CThe President requested the Department of Industry and Trade to coordinate with Hai Phong Electricity Company Limited to increase the capacity of 110/22kV transformers at Cat Hai 110kV Transformer Station, ensuring enough capacity to serve the needs of Ben No. 3 and 4 Project (expected about 19,000kVA); Hai Phong Water Supply Joint Stock Company considers and builds a water supply pipeline connecting the existing HITC Port to the project fence.
Regarding the procedures for implementing the project, the Vice Chairman requested the Investor to coordinate with the consulting unit to inspect and review, and at the same time need to shorten the time, speed up the progress of project commencement earlier, striving to complete both wharves by 2023. Regarding the general traffic route, not only to exploit wharfs 3 and 4 but also to serve the exploitation of the next wharves of Lach Huyen Port Area, the Vice Chairman requested Hai Phong Port to soon report to the Ministry of Transport and establish a project now.
Minh Hao