Vice Chairman of the City People's Committee Nguyen Duc Tho visited the entire route to check the progress of the projects. (Haiphong.gov.vn) – On the afternoon of April 20, Vice Chairman of the City People's Committee Nguyen […]


Vice Chairman of the City People's Committee Nguyen Duc Tho conducted a field trip along the entire route to check the progress of the projects.
(Haiphong.gov.vn) - On the afternoon of April 20, Vice Chairman of the City People's Committee Nguyen Duc Tho conducted a field trip across the entire route to check the progress of investment projects to build a coastal road section through Hai Phong city and 9km in Thai Binh province in the form of public-private partnership and an investment project to expand the coastal road section through Hai Phong city from Provincial Road 353 to the bridge. Thai Binh. Accompanied by representatives of leaders of departments, branches, localities and relevant units.

Vice Chairman of the City People's Committee Nguyen Duc Tho assessed that the progress of implementing the BOT Project has not yet made much progress.
Through field inspection, for the BOT Project, regarding site clearance work, currently Tien Lang district has 7 households that have not received money and have not handed over the site, Kien Thuy district has 1 household that has only partially handed over; In Thai Binh province, there are still 17 households that have not handed over their premises.

Up to this point, the overall construction volume of the entire route is estimated to reach 35%.
Regarding construction work, up to now the line section in Do Son district has reached 46% of the contract value, the line section in Kien Thuy district has reached 48%; Van Uc bridge reached 60%; The section in Tien Lang district reached 6%; Thai Binh bridge reached 6% of contract value. The 9km section in Thai Thuy district, Thai Binh province is estimated to have an implementation value of 55% of the contract. Overall, the entire route reaches 35% of the volume.
For the coastal road expansion project, construction has been implemented since July 2021, to date, the project has reached nearly 28% of the contract value. On the entire route, the contractor consortium is simultaneously constructing the road and Lach Throat bridge, district road 212 overpass, Kenh Nam bridge and other auxiliary items.

Vice Chairman of the City People's Committee Nguyen Duc Tho requested to speed up the construction progress to ensure the project is completed as planned.
Emphasizing the very important significance of the projects in forming a connected, inter-regional transportation network, creating motivation for the city's socio-economic development, requiring the active participation of the Party Committee, local authorities, the consensus of the people, the drastic determination of the Investor in site clearance and construction of the project, through field inspection of the entire route, Vice Chairman of the City People's Committee Nguyen Duc Tho assessed The price and progress of the BOT project have not yet made much progress.
The Vice President criticized the project enterprise for not seriously implementing the city's direction that after signing the credit contract, they must focus on project construction. The Vice Chairman requested a review of the contractors' capacity and needed replacement to ensure the progress of the project as planned.
The Vice Chairman also requested Tien Lang district to completely resolve the land problems of the remaining 7 households by May 10; Assign the Project Management Board and contractors to focus on human resources and construction equipment; Departments and branches are assigned to coordinate closely with relevant units to guide localities in compensation and site clearance work, ensuring that projects are implemented smoothly and on schedule.
Minh Hao; Photo – Dam Thanh