(Haiphong.gov.vn) - On the morning of April 28, Chairman of the City People's Committee Nguyen Van Tung inspected and listened to the progress report of the investment project to renovate and upgrade Ngo […]

(Haiphong.gov.vn) – On the morning of April 28, Chairman of the City People's Committee Nguyen Van Tung inspected and listened to a progress report on the investment project to renovate and upgrade Ngo Gia Tu Street (section from the old Airport gate to the inter-ward road); site inspection of Lot 20, 21 of Nga 5 New Urban Area Project – Cat Bi Airport; Investment project to build the Administrative and Political Center of Ngo Quyen district and Green park construction project at 53 Lach Tray, Lach Tray ward. Attending were representatives of leaders of departments, branches, localities and relevant units.
Investment project to renovate and upgrade Ngo Gia Tu street (section from the old airport gate to the inter-ward road) with a length of 1.86km; Total investment is more than 242.5 billion VND, land area used is 4.6 hectares. To date, the contractor has organized construction with a construction value of 60 billion VND. Currently, the construction of the project is facing problems with site clearance related to defense land. Regarding the progress of site clearance for Lot 20 and 21 of the new urban area project at intersection 5 - Cat Bi airport, 6.2 hectares have been cleared, while 1.6 hectares are being cleared for 93 households. In particular, the compensation and support plan for 56 households with an area of 10,042m2 was approved. To ensure the site, Ngo Quyen district asked the city for advice on forcibly confiscating land for 6 households; consider, approved other support for 5 households whose compensation plans were approved in the T30 node area connecting Nguyen Binh Khiem street.
The investment project to build the Administrative and Political Center of Ngo Quyen district has a scale of 13,600 m2, total investment of more than 254.1 billion VND. Up to now, 9,500m2/13,600m2 have been liberated, there are still 4,100m2 of 40 cases that have not been released. Currently, the district is highly focused on completing site clearance work in May 2021 to serve the start of project implementation. The District recommends that the Departments of Construction and Industry and Trade soon appraise construction drawing designs as a basis for approval and organize bidding to select contractors. At the same time, it is proposed that the City People's Committee agree to the policy of assigning the District People's Committee to carry out the task of preparing investment and being the investor of the 100m road section from Le Hong Phong street to T30 street to synchronize the infrastructure.
For the project to build a green park at 53 Lach Tray, Lach Tray ward with a scale of 22 thousand m2, it is expected that in May 2021 the district will approve the investment policy; The project will start construction in July 2021 and be put into use in January 2022. Ngo Quyen District requested that the city pay attention to allocating capital to ensure project implementation progress in 2021.

City People's Committee Chairman Nguyen Van Tung chaired the meeting
After inspecting the projects and listening to reports from departments, branches, localities and units, Chairman of the City People's Committee Nguyen Van Tung welcomed the People's Committee of Hai An District, People's Committee of Ngo Quyen District and units for their efforts in carrying out site clearance work and speeding up the progress of projects. To continue implementing projects on schedule, Chairman of the City People's Committee Nguyen Van Tung requested localities and units to urgently carry out the following tasks:

Chairman of the City People's Committee checks the progress of the investment project to renovate and upgrade Ngo Gia Tu Street
For the investment project to renovate and upgrade Ngo Gia Tu Street, the Chairman of the City People's Committee emphasized that this is an urgent project. Voters and city people have made recommendations on the environment and traffic, therefore, agreeing to allocate 80 billion VND from 2020 spending savings for the project. The People's Committee of Hai An and Ngo Quyen districts directed contractors to speed up construction progress, ensure traffic safety and project quality, and strive to open the route in 2021.

Chairman of the City People's Committee listened to petitions from households at group 7, Dong Chinh, Dang Giang ward (Ngo Quyen district)
Through site inspection of Lots 20, 21 of the New Urban Area Project of Junction 5 - Cat Bi Airport, listening to the recommendations of households and the opinions of the Department of Natural Resources and Environment, the Chairman of the City People's Committee assessed that the People's Committee of Ngo Quyen District has adequately compensated and cleared the site, ensuring the rights of households and in accordance with the law, so the recommendations have no basis to be considered. consider resolving. The Chairman of the City People's Committee requested households to seriously hand over the site to the construction contractor to ensure the progress of the project. Ngo Quyen District People's Committee carries out forced land recovery in accordance with the law.

Chairman of the City People's Committee Nguyen Van Tung inspected the investment project to build the Administrative and Political Center of Ngo Quyen District
For the investment project to build the Administrative - Political Center of Ngo Quyen district, the Chairman of the City People's Committee assigned the People's Committee of Ngo Quyen district to clear the land for households with land located in the project foundation area in May 2021, striving to start the project in early June 2021. At the same time, the Chairman of the City People's Committee assigned the People's Committee of Ngo Quyen district to implement procedures to start the green park construction project at 53 Lach Tray in early July 2021.
Nguyen Hai