Online mailbox
Receiving feedback and proposals from organizations and individuals.

On November 28, 2023, the People's Committee of Hai Phong city issued Decision No. 4086/QD-UBND on the Decision approving the investment policy and approving [...]

On November 28/November/2023, the People's Committee of Hai Phong city issued Decision No. 4086/QD-UBND on the Decision approving the investment policy and approving the investor The Exhibition Center Project display, introduce and sell Hyundai Thanh Cong Hai Phong products invested by Thanh Cong Group Joint Stock Company with some main contents as follows:
1. Investor: Thanh Cong Group Joint Stock Company
Certificate of business registration as a joint stock company, business code 0100831174 issued by the Business Registration Office under the Hanoi Department of Finance, first registered on October 24, 2008, registered for the 12th change on January 29, 2021.
2. Project name: Hyundai Thanh Cong Hai Phong product display, introduction and sales center project.
3. Project objective: Construction of the Hyundai Thanh Cong Hai Phong product display, introduction and sales center to serve the Group's strategic business goals, contributing to completing the system of public works in Le Chan district and Hai Phong city.
4. Project scale:
– Area of land for project research: About 4,230 m2.
– Land area allowed for construction in accordance with planning: About 3,260 m2 (except for the land area within the planned road opening line of about 970 m2).
– Products and services provided: Product display and introduction store.
– Expected architectural scale of construction:
+ Construction area 2,119 m2; Construction floor area is about 8,476 m2 (excluding basement floor area); The number of floors is 04 floors + 01 basement; Construction height is from 18-25 m; Construction density 65%; Land use coefficient 2.6 times.
+ Traffic and landscape trees are 1,141 m2.
The scale and architectural planning criteria are officially determined according to the shortened detailed planning (General ground planning) approved by competent authorities, ensuring compliance with relevant planning according to current regulations.
5. Total investment capital and expected capital mobilization plan: 120,000,000,000 VND (in words: One hundred and twenty billion VND). In which: Investor's capital contribution: 120,000,000,000 VND (Equity); Mobilized capital: 0 VND.
6. Operational time of the project: From the date the City People's Committee approved the investment policy and approved the investor until May 2058.
7. Project implementation progress: 33 months from the date the City People's Committee approved the investment policy and approved the investor.
8. Construction location: No. 742 Nguyen Van Linh Street, Niem Nghia Ward, Le Chan District, Hai Phong City.
9. Investment incentives and support: Follow relevant current legal regulations.