(Haiphong.gov.vn) - On the morning of August 14, Standing Vice Chairman of the City People's Committee Nguyen Xuan Binh and representatives of leaders of departments, functional branches, units and localities […]

(Haiphong.gov.vn) - On the morning of August 14, Standing Vice Chairman of the City People's Committee Nguyen Xuan Binh and representatives of leaders of relevant departments, functional branches, units and localities inspected the progress of implementation of projects: Route from Doan Lap intersection - Han bridge - National Highway 37; route from Doan Lap intersection - Dang bridge - National Highway 37; investment project to build Hoa River bridge and project to renovate and upgrade the road from Lang Am bridge to Nhan Muc bridge.
Permanent Vice Chairman of the City People's Committee Nguyen Xuan Binh inspected the construction situation on the route from Doan Lap intersection - Dang bridge – QL.37.According to the report, the investment project to renovate and upgrade the road from Doan Lap intersection - Han bridge - National Highway 37, the Project Management Board has coordinated with the locality to review the progress of handing over the site, mainly handing over residential land. Currently, both Tien Lang and Vinh Bao districts still have 143 households that have not handed over the site. For the route from Doan Lap intersection - Dang bridge - National Highway 37, both districts currently have 98 households that have not yet handed over their land. The Project Management Board said that after reaching agreement with the People's Committee of Tien Lang district and the People's Committee of Vinh Bao district, the site will be handed over within 5 days from the date of receiving funds to pay households; It is expected that by August 20, 2019, all premises will be handed over. Regarding construction, contractors are urgently mobilizing equipment and overcoming site delays to speed things upAccording to progress, if they receive enough space, contractors will strive to basically complete the route in September 2019.
Inspecting the field at the scene, the Standing Vice Chairman of the City People's Committee assessed that up to now, the site clearance progress of Tien Lang and Vinh Bao districts has made progress, the construction situation has changed, but the amount of work is still very much. The Standing Vice Chairman requested relevant departments and branches to urgently approve and pay site clearance costs to households. At the same time, the Project Management Board was assigned to make efforts to urge and direct contractors to focus on construction. For some contractors with poor awareness and not organizing construction after handing over the site, review and make a record of progress violations. Definitely, where there is a site, construction must be organized to ensure safety and overall progress of the project, the Permanent Vice Chairman emphasized.
For the investment project to renovate and upgrade the road connecting Lang Am bridge to Nhan Muc bridge, Vinh Bao district, regarding site clearance work, there is still 01 household on the new route that has not yet handed over the site. The district is actively campaigning and propagandizing for this household to soon hand over the site to the contractor. Regarding road construction, up to this point, the total construction volume of the entire route has reached about 90% of the contract volume. The contractors focused on many construction tasks and committed to complete the construction of asphalt concrete mats on the new road side before August 30, 2019; Chanh Duong bridge (km20 + 625) will have the concrete bridge deck completed before August 22, 2018; The items of railings, asphalt concrete, bridgehead roads... completed before August 30, 2019; Complete construction of infrastructure itemsTechnical specifications of 4 resettlement areas before August 30, 2019...
At the inspection, Permanent Vice Chairman Nguyen Xuan Binh requested that the Project Management Board, along with local authorities and contractors, continue to focus on the final construction items to absolutely ensure progress quality, and at the same time, based on the actual situation, report to the city's competent authority for consideration and decision to prepare a plan for technical traffic opening on the occasion of September 2, 2019.
Hoa River bridge in Thai Thuy district (Thai Binh province) is currently 14 days behind schedule. plan.Investment project to build Hoa River bridge connecting Vinh Bao district, Hai Phong city and Thai Thuy district, Thai Binh province. Currently, site clearance work in Vinh Bao district has been completed and 100% of the site has been handed over to the construction contractor; On the side of Thai Thuy district (Thai Binh province), as of August 13, 2019, the land area handed over to the contractor reached 67%; Project construction value is estimated at 40.5% of the contract.
In terms of construction implementation, the items on the Vinh Bao bank basically ensure the required progress, it is expected that the first beam slab will be installed at the end of August 2019. However, the items on the Thai Thuy bank are 14 days behind schedule due to not having enough space, the contractor will have to find solutions to catch up with the completion schedule by the end of 2019.
At the scene, Permanent Vice Chairman of the City People's Committee Nguyen Xuan Binh noted the good progress of project construction. With the problems in site clearance work in Thai Thuy district, the Vice Chairman requested the district to continue to mobilize the remaining households to soon resolve land recovery procedures and hand over the site to the construction contractor. The Vice Chairman also requested that the Project Management Board proactively coordinate with localities and relevant units of Thai Binh province, closely following the site clearance situation to ensure project progress.
Minh Hao