(Haiphong.gov.vn) - On the afternoon of July 28, Standing Vice Chairman of the City People's Committee Le Anh Quan inspected the implementation of the infrastructure construction investment project [...]

(Haiphong.gov.vn) - On the afternoon of July 28, Standing Vice Chairman of the City People's Committee Le Anh Quan inspected the implementation of the technical infrastructure investment project related to the North Cam River New Urban Area. Accompanied by leaders of relevant departments, branches, units and Thuy Nguyen district.

Permanent Vice Chairman of the City People's Committee Le Anh Quan inspects the Project
According to the report of the Urban Development and Civil Construction Investment Project Management Board, for the investment project to build technical infrastructure of the new urban area North of Cam River, as of July 28, 2021, the Hoang Van Thu bridge construction package has reached 99.5% of the work volume; The bidding package for constructing Cam River left dike reached 45.65% of the work volume; The main transportation system construction package reached 48.1% of the work volume; The bidding package for building the technical infrastructure system reached 55.6% of the work volume. For the investment project to build technical infrastructure in the North Cam River resettlement area (phase 2), by July 26, 2021, 90% of the work volume has been reached, expected to be completed in December 2021.
However, currently, the bridge leading to the right branch north of Hoang Van Thu bridge still has 40 households that have not cleared the site, so it has affected the construction progress of Hoang Van Thu bridge; For the construction of Cam River's left dyke, main traffic and technical infrastructure systems, the contractor has received the construction site but the site area is still small, interspersed with the unrecovered land area, so it is not guaranteed to serve the construction and construction of temporary auxiliary works; Households have not cleared the land, affecting the drainage of the Project...

Permanent Vice Chairman of the City People's Committee Le Anh Quan spoke at the meeting
After inspecting the reality and listening to the report, Standing Vice Chairman of the City People's Committee Le Anh Quan acknowledged the efforts and active participation of Thuy Nguyen district and related departments, branches and units in implementing the investment project to build technical infrastructure related to the North Cam River New Urban Area. Emphasizing the importance of the Project, the Standing Vice Chairman of the City People's Committee requested Thuy Nguyen district to be more active in assigned tasks, doing a good job of propaganda and mobilizing people in site clearance work, along with arranging resettlement with the remaining households in the Project area to hand over the site to the construction contractor; Quickly complete relevant documents and procedures so that departments and branches can give their opinionsEnsure project progress; Pay attention to the work of ensuring security and order, and take strict measures to deal with those who entice and incite to affect the implementation of the Project. For the Urban Development and Civil Construction Investment Project Management Board, it is necessary to speed up the implementation progress when there is clean ground, to avoid re-encroaching on areas that have been cleared.