(Haiphong.gov.vn) - On the morning of August 11, the working group of Le Chan District Party Committee led by comrade Le Trung Kien, City Party Committee member, Secretary of the District Party Committee went to […]

(Haiphong.gov.vn) - On the morning of August 11, the Le Chan District Party Committee's working group led by comrade Le Trung Kien, City Party Committee member, District Party Secretary, inspected the progress of site clearance work on the Ho Sen - Cau Rao 2 road construction investment project, the section from Nguyen Van Linh intersection to Cho Con street intersection and the A51 resettlement area in Vinh ward. Niem, Le Chan district.

The investment project to build Ho Sen - Cau Rao 2 road is being accelerated by construction contractors
The investment project to build Ho Sen - Cau Rao 2 road, the section from Nguyen Van Linh intersection to Cho Con street intersection has a total area of land recovered: 59,254.5 m2 (including organizations, roads and a total of 470 households/539 plots of land) in the wards of Du Hang Kenh, Du Hang, Hang Kenh and Trai Cau ward, Le district. Legs.

Le Chan District Party Committee's delegation listened to the progress of project implementation
Up to now, Le Chan District People's Committee has completed the inventory of 470 households = 539 plots (in 3 wards); with total approved amount: 871,766 billion VND; area 36,294.29 m2. The District People's Committee has paid compensation and support to 359/470 households (Du Hang Kenh ward 207/313 households, Hang Kenh ward 90/95 households, Du Hang ward 62/62 households) with a total cost of 708.774 billion VND with an area of 25,709.43 m2, remaining 5.098 billion VND. The area has been temporarily handed over to the investor: 24,219.13 m2.

Demolition and construction of houses that have handed over the premises
For the 21 households that have received money but have not yet handed over the premises, the District People's Committee continues to direct departments, units and People's Committees of the wards to encourage households to move assets and hand over the premises before August 15, 2020.


Le Chan District Party Committee's working group talked and listened to the opinions of households whose land was recovered
After inspecting the actual project site, the Le Chan District Party Committee's working group went to households whose land was recovered to directly listen to opinions, thoughts, and wishes. At the same time, clearly explain to households each issue related to the process, order, and procedures for land recovery and request departments, branches, branches, and local authorities to continue to coordinate with households, inspect and thoroughly review procedures and regulations, creating maximum conditions for people within the framework of the law. The delegation also expressed their wish for the people to agree, quickly receive money, relocate, hand over the site, coordinate and support the government to soon complete the site clearance work so that the project can be implemented as planned, contributing toBuild Le Chan district in particular and Hai Phong city in general to be civilized and modern, serving the lives of the people.
Hoang Tung