(Haiphong.gov.vn) - On the morning of February 26, Vice Chairman of the City People's Committee Nguyen Duc Tho inspected and heard reports on the preparation of conditions to bring the wharf [...]

(Haiphong.gov.vn) - On the morning of February 26, Vice Chairman of the City People's Committee Nguyen Duc Tho inspected and heard reports on the preparation of conditions to put Dong Bai ferry terminal (Cat Hai district) into operation. Also attending the work were representatives of leaders of departments, functional branches and related units.

Vice Chairman of the City People's Committee Nguyen Duc Tho inspected the field at the waiting area.
At the meeting, Deputy Director of the Department of Transport Nguyen Minh Tuan said that up to now, Cat Ba Sun Company Limited - Investor of Dong Bai ferry terminal has coordinated with the Management Board of Hai Phong Economic Zone to carry out the project acceptance work; Construction of stone dumping under wharf; Build shelters to protect motorcyclists and pedestrians while moving from the waiting room to the ferry; Agree with the terminal operator to have an optimal design with operating procedures, ensuring beauty and synchronization with the modern landscape architecture of the new ferry terminal. For Hai Phong Waterway Traffic Assurance Joint Stock Company, the unit has completed the test run of Dong Bai ferry terminal; At the same time, we are coordinating with the ferry building unit to rent more ferries; rentwaiting room, operating house and auxiliary works serving the operation of Dong Bai ferry terminal.

Panoramic view of Dong Bai new ferry terminal (Cat Hai district).
On the part of the Department of Transport, it has also coordinated with the Hai Phong Economic Zone Management Board to guide and urge Cat Ba Sun Co., Ltd. to prepare conditions for the new ferry terminal to come into operation; Organize the installation of traffic sign systems in the ferry wharf area and new wharf access routes, and at the same time check and review the capacity of Hai Phong Waterway Traffic Assurance Joint Stock Company to provide public passenger transport services by ferry, and evaluate the technical condition and safety level of the Company's existing ferries.
Vice Chairman of the City People's Committee Nguyen Duc Tho requested relevant sectors and units to urgently complete procedures and ensure conditions to officially put Dong Bai ferry into operation from March 1, 2024
Through inspection and listening to reports from relevant agencies, Vice Chairman of the City People's Committee Nguyen Duc Tho requested units to urgently complete all procedures for handing over common technical infrastructure works, arranging waiting areas, operating houses and auxiliary works to be leased to the ferry service provider at Dong Bai ferry terminal to ensure conditions and operating activities according to regulations. Vice Chairman Nguyen Duc Tho also assigned the Department of Transport to review and organize the installation of a system of signs and signs leading to the ferry terminal and the route leading to the new Dong Bai ferry terminal; Along with that, preside over the Maritime Port Authority, Border Guard and Cat Ba Sun Co., Ltd. to complete the passenger wharf infrastructure so that it can be put into operation on April 30 - May 1 this year. DeputyThe Chairman also asked the Waterway Traffic Assurance Joint Stock Company to proactively take operational measures to ensure vehicles get on and off the ferry safely and conveniently, in addition to establishing a process for exploiting and operating the new Dong Bai ferry terminal.


In recent days, Hai Phong Waterway Traffic Assurance Joint Stock Company along with related units have continuously organized trial ferry runs at Dong Bai ferry terminal.
According to the plan, starting from 5:00 a.m. on March 1, 2024, the first ferry of Dong Bai ferry terminal will officially come into operation, replacing Got ferry terminal. With modern facilities and higher transportation capacity, putting the new Dong Bai ferry terminal into operation is expected to overcome congestion at Got ferry terminal, especially during peak periods, creating convenience for people and tourists when coming to Cat Ba island. According to statistics from the Waterway Traffic Assurance Joint Stock Company, currently the average number of passengers passing through the Got - Cai Vieng ferry port per day is about over 3,700 passengers, the average number of vehicles passing through the ferry per day is about nearly 750 vehicles. On weekends and holidays, April 30 - May 1, the number of people and vehicles increases1.5 to 2 times, during peak tourist months, ferries often operate at full capacity, leading to overload and congestion.../.