Investment project to build Quang Thanh bridge connecting Hai Phong city and Hai Duong province. Construction time according to the contract is 15 months, starting [...]

Up to now, the contractor has basically completed the construction work. The remaining job is to paint road markings. It is expected that the Ministry of Transport will inspect the acceptance and completion of the project before June 20, 2021.

Quang Thanh Bridge was built in An Lao district, Hai Phong city and Thanh Ha district, Hai Duong province. The bridge is permanently built of reinforced concrete and prestressed reinforced concrete across the Van Uc River. Bridge length is 536m, bridge width is 12m, bridge consists of 10 spans. This is a level I traffic project.
The construction contractor is a joint venture of Thang Long Bridge 3 Joint Stock Company - HJC Investment - Construction Group Joint Stock Company and Thang Long Corporation. Construction time according to the contract is 15 months, starting on May 16, 2020.
The project has a total investment of 398,600 million VND, of which the central budget capital is 156,696 million VND, including: Construction costs, project management costs, consulting costs, and other costs.
Hai Phong city budget is 239,304 million VND, including: Construction costs, project management costs, consulting costs, other costs and site clearance costs in Hai Phong city..
Hai Duong province's budget is 2,600 million VND to cover site clearance costs in Hai Duong province.