Vice Chairman of the City People's Committee Nguyen Duc Tho inspected the scene. (Haiphong.gov.vn) - On the afternoon of December 9, Vice Chairman of the City People's Committee Nguyen Duc Tho conducted a field inspection [...]


Vice Chairman of the City People's Committee Nguyen Duc Tho inspected the scene.
(Haiphong.gov.vn) – On the afternoon of December 9, Vice Chairman of the City People's Committee Nguyen Duc Tho on-site inspected the progress of implementation of the Ho Sen - Cau Rao 2 road construction investment project, section from Nguyen Van Linh intersection to Cho Con street intersection. Accompanied by representatives of relevant sectors, functional units and localities.
According to the report of the Traffic Construction Investment Project Management Board, up to this point, the land clearance work of the trunk road from Nguyen Van Linh intersection to Cho Con street intersection has been basically completed, with only 02 households remaining with about 25md, so the construction unit has not yet connected the drainage system, technical trenches and asphalt concrete mats... Currently, the contractor is constructing sidewalks and installing the system. lighting, road painting, traffic sign installation and median planting; The implementation volume is estimated at 91% of the contract value.

The section from Cho Con street to To Hieu street. Photo: Hong Phong
For site clearance work, the section from Cho Con street to To Hieu street has a total area of recovery of 8,491.5 m2, including traffic land, agency headquarters, non-agricultural land and residential land. Currently, Le Chan district has completed the inventory and is making a plan for compensation and support, and at the same time propagating and campaigning for Construction Joint Stock Company No. 1, Construction Joint Stock Company No. 3 and Le Chan District General Hospital to demolish structures on an area of about 625.8 m2...
Through inspection of the entire route and listening to reports at the meeting, Vice Chairman of the City People's Committee Nguyen Duc Tho highly appreciated the efforts and determination of Le Chan district and the Project Management Board in site clearance and construction implementation. Up to this point, the project is being implemented according to the approved adjusted schedule. The Vice Chairman emphasized that the Ho Sen - Cau Rao 2 road construction investment project has a particularly important meaning in beautifying and expanding urban space, and at the same time contributing to minimizing traffic congestion in the city center area. Therefore, functional agencies, units and localities need to coordinate closely and continue to review shortcomings in the clearance work of phase 2 of the project and compare them.Reviewing the land origin and legality, please consult the Departments and branches. For site clearance work of phase 3 of the project, the Vice Chairman requested Le Chan district to publicly announce the compensation plan for households by December 15, 2020, and at the same time propagate and mobilize people to hand over the site before December 31, 2020.

Panoramic view of Lotus Lake - Cau Rao 2 route. Photo: Hong Phong
Emphasizing the statement that the Ho Sen - Cau Rao 2 route will be a point route, a model central route of the city in the near future, the Vice Chairman requested the Project Management Board to coordinate with the Department of Transport to review signs, warnings, road markings... to ensure traffic safety; The Department of Construction coordinated with Le Chan district to complete regulations to protect the route, prevent encroachment, and preserve the landscape of the model route to ensure safety and urban beauty of the route after completion; request that Hai Phong Electricity Company Limited proactively report to the Northern Electricity Corporation to plan the investment in the project of undergrounding the electrical system of the route and implement it in 2021. The Vice Chairman also noted that the contractors willDuring the construction process, it is necessary to strengthen management and ensure environmental hygiene.