On the afternoon of April 11, Standing Vice Chairman of the City People's Committee Le Khac Nam met with leaders of related departments, branches and units. inspection officerprogress of the green park project from the old Tam Bac bus station to the foot of the Tam Bac road bridge - Phase 1 and the implementation status of the Phase 2 project.
Up to this point, Le Chan district has completed the inventory of 203/250 households. Relocation and clearance of medical facilities, the district has received the handover of the site from the Viet Tiep 2 Project Management Board and is preparing a dismantling cost estimate; Currently, there are 5 medical facilities that have relocated but have not completed the procedures for handing over the premises; Methadol treatment facility and Traditional Medicine Hospital are waiting for the city to approve funding to build a new headquarters. The Department of Health is proposing that the city invest in building a number of garage items and specialized houses for the 115 Emergency Center. For Huong Duong Kindergarten in Le Chan district, it is also expected to arrange space to move towards Lan Be street.
After listening to comments at the meeting, Permanent Vice Chairman of the City People's Committee Le Khac Nam affirmed that this is an important project to beautify the city's urban appearance. Although there have been many changes, the implementation progress up to this point is still slow compared to requirements, especially the preparation of site clearance compensation plans for households within the scope of phase 2 project, and the relocation of units under the Department of Health. The Vice Chairman requested Hong Bang district to urgently coordinate with functional agencies to approve the price of resettlement land, while continuing to pay attention to monitoring and ensuring project quality and speeding up project progress to serve the city's major holidays in May. For phase 2 of the project, Le Chan district needs to focus on public worksPropaganda and advocacy work so that people understand the purpose and meaning of the project, in addition, it is necessary to coordinate with functional agencies to determine the compensation price to support the price of resettlement land to ensure reasonableness; Regarding the construction of Huong Duong Kindergarten, the Vice President requested that basic procedures be completed soon. He also requested the Department of Finance and the Department of Finance to arrange capital sources to ensure project implementation progress.
Tram Bau