Chairman of the City People's Committee inspected the Project to upgrade the Water Trough route. (Haiphong.gov.vn) – On the morning of January 6, Chairman of the City People's Committee Nguyen Van Tung and leaders [...]

(Haiphong.gov.vn) - On the morning of January 6, Chairman of the City People's Committee Nguyen Van Tung and leaders of relevant departments, branches, units and localities inspected the progress of a number of key projects in Thuy Nguyen district and Hai An district.
According to a report from Thuy Nguyen district, the investment project to renovate Provincial Road 359 from Binh bridge to Trung Ha commune has a length of more than 8km and is designed according to the type of main and secondary urban street. Currently, at the cleared route sections, the joint venture contractor is actively implementing construction, striving to complete the asphalt concrete layer before the Lunar New Year, complete sidewalk paving, install lighting poles, and move the electrical system through Nui Deo town; Installing sidewalks, pouring concrete to line the sidewalk from the gate of Regiment 238 (km3+200) to the end of Thuy Son commune...
However, through on-site inspection, the Chairman of the City People's Committee pointed out that there are many places where site clearance work has been completed, but the contractor has not yet mobilized vehicles and machinery for construction while there are only a few days left until the Lunar New Year. The Chairman requested Thuy Nguyen district to focus on directing consulting units and contractors to speed up project construction progress to complete items as planned.
The Chairman requested that before the Lunar New Year, the installation of sidewalks and concrete paving of the Provincial Road improvement investment project must be completed. 359.For the investment project to build and renovate the Water Trough road from the foot of Binh bridge connecting to road 359 in Nui Deo town, because the investment project to build a resettlement area is implemented later and independently of the Water Trough Road project, thus greatly affecting the construction progress as well as the overall progress of the project. Chairman Nguyen Van Tung requested that Thuy Nguyen district continue to promote compensation and land clearance work to be able to open roads in the Northern Cam River area, and at the same time speed up the construction progress of resettlement area infrastructure, focusing resources to strive to complete the construction of the Water Trough Road Project in 2020.
Inspecting the construction work in the An Kim Hai ditch area (corner of Le Hong Phong street and Nguyen Binh Khiem street), the Chairman requested the city's functional departments and branches to coordinate in reviewing and implementing land recovery procedures; assign the Department of Natural Resources and Environment to install boundary markers and soon hand over the boundary markers to the Project Management Board to urgently construct and expand the road; request Minh Chau Service Joint Stock Company to redecorate the walls and fences of this area to make it spacious, clean and beautiful. For site clearance and orderly handling of construction in the urban trunk road intersection area under the Urban Transport Development Project and Le Hong Phong Street. The Chairman assigned Hai An district to proactively implement Decisions on enforcement of land recoveryAccording to legal regulations in cases of land encroachment and illegal construction...
Minh Hao