(Haiphong.gov.vn) - On the afternoon of January 31, Standing Vice Chairman of the City People's Committee Le Anh Quan inspected and listened to reports on the implementation of construction investment projects [...]

(Haiphong.gov.vn) - On the afternoon of January 31, Standing Vice Chairman of the City People's Committee Le Anh Quan inspected and listened to reports on the implementation of construction investment projects in the North Cam River area, Thuy Nguyen district.
>Check the progress of construction investment projects in the North Cam River area.
According to the report of the Investor and construction contractors, the Investment and Construction Project of the City Political-Administrative Center, Transportation System and Synchronous Technical Infrastructure System in North Cam River Urban Area As of January 30, 2024, the Eastern region has completed the construction of reinforced concrete structures for all blocks of buildings, other contents reaching from 60% to 95% of the volume. In the western area, the construction of reinforced concrete structures of all blocks, basement construction, wall plastering, drilling of soil cement piles, infrastructure of the area connecting to the square... reached from 33% to 95%. Roads with 5 categories achieved from 41% to 100%. Other items are expected to be completed in November 2024.
>Some pictures at project construction sites.
For the Investment and Construction Project of the City Convention - Performance Center and Synchronous Technical Infrastructure System, as of January 30, 2024, the City Convention - Performance Center has completed the construction of reinforced concrete for the basement, floors, and foundations of floors 2,3,4,5,6; Construction of the 6th floor and some other content is underway. The category of roads and outdoor infrastructure with 5 components has been completed from 66% to 100%. For other items, it is expected to be completed from March 2024 to January 2025.

>Contractors are focusing on constructing the project.
>Permanent Vice Chairman of the City People's Committee Le Anh Quan directed at the project site.
Speaking at the construction site, Standing Vice Chairman of the City People's Committee Le Anh Quan acknowledged the efforts of the construction units in ensuring the progress of the project. At the same time, please note that units must arrange the construction site neatly, ensure safety and security before the Lunar New Year holiday and start work immediately after the holiday. The Standing Vice Chairman of the City People's Committee directed the City People's Committee Office to coordinate with departments and branches to urgently complete documents for sidewalk items and fountains in the square area to complete construction work on May 13, 2024.
>
>
>On this occasion, Permanent Vice Chairman of the City People's Committee Le Anh Quan gave Tet gifts and encouraged workers of construction units.