(Haiphong.gov.vn) - On the morning of November 17, Vice Chairman of the City People's Committee Le Trung Kien chaired a hybrid in-person and online meeting with departments, agencies, sectors, project developers, and 114 communes, wards, and special zones across the city to hear progress reports on the implementation of the public investment capital disbursement scenario and site clearance work in November 2026.
Also attending at the City Political - Administrative Center venue were representatives of the leadership of municipal departments and sectors: Finance, Construction, Industry and Trade, Agriculture and Environment, Home Affairs, Science and Technology, the City Military Command, the City Police, Regional State Treasury III, the Hai Phong Economic Zone Authority, the City People's Committee Office, and leaders of specialized construction investment project management boards under the city.
According to the report of the Department of Finance, as of November 15, 2026, the total public investment capital disbursed across the city reached VND 36,479 billion; of which, the plan assigned for 2026 reached VND 35,943 billion, equal to 93% of the plan assigned by the Prime Minister (reaching 97.3% after excluding the 5% expenditure savings) and 76% of the plan assigned by the City People's Council and People's Committee; carried-over capital disbursement reached VND 536 billion (reaching 91.2% of the plan). Across the city, 78 out of 125 project developers and localities achieved a disbursement rate of 86% or higher, notably the Hai Phong Civil and Industrial Works Construction Investment Project Management Board and many communes and wards achieving over 95%.

Regarding site clearance, according to data aggregated on the Intelligent Operation Center (IOC) system of the Department of Agriculture and Environment, as of the end of November 15, 2026, the entire city had 434 projects requiring site clearance across 108 localities with a total area of over 57.3 million m²; to date, cleared land has reached 70.9% of the total area (over 40.6 million m²) with compensation payments totaling over VND 25,405 billion. In particular, 221 public investment projects scheduled for completion in 2026 achieved site clearance across 80.7% of their area (155 out of 221 projects completed). Site clearance progress on key projects such as the Lao Cai - Hanoi - Hai Phong railway reached 75.8%, the Hanoi - Quang Ninh high-speed railway reached 76.3%, industrial park infrastructure reached 73.6%, industrial cluster infrastructure reached 81.9%, and resettlement areas reached 77.3%.

Discussing at the meeting, leaders of People's Committees of communes and wards with slow disbursement and site clearance rates frankly analyzed the causes, clarifying bottlenecks arising at the grassroots level following the operation of the two-tier local government model, such as: complex land documentation across multiple periods, time-consuming determination of land origins; certain households not yet agreeing with compensation unit prices or awaiting resettlement land allocation; and the slow transfer of site clearance funds by some project developers. Concurrently, localities also proposed that the city promptly and flexibly reallocate capital from delayed projects to projects with good disbursement capacity, expedite the approval of plans to handle surplus headquarters and public assets after reorganization, and provide guidance on medium-term public investment procedures.

Based on the recommendations of localities, representatives of the leadership of the Departments of Finance, Agriculture and Environment, Construction, Science and Technology, along with specialized Project Management Boards, directly exchanged views, addressed queries, and proposed solutions to resolve obstacles regarding project adjustment appraisal procedures, handling of construction contracts, land use fee collection mechanisms for resettlement, year-end capital reallocation plans, as well as upgrading progress alert features on the IOC intelligent operation system.

Delivering concluding remarks at the meeting, Vice Chairman of the City People's Committee Le Trung Kien acknowledged and commended the great efforts and high determination of departments, sectors, project developers, and localities that placed the city's public investment capital disbursement rate among the leading group nationwide. Emphasizing that time in 2026 is running short, the Vice Chairman of the City People's Committee requested the entire political system to focus intensely and strive to achieve 100% disbursement of the assigned capital plan in line with the instructions of the Standing Committee of the City Party Committee (completing the capital plan assigned at the beginning of the year before November 30 and fully disbursing additional capital allocations in December 2026), considering this a critical criterion for assessing task performance and year-end commendation ranking.

The Vice Chairman of the City People's Committee requested communes, wards, and special zones to decisively resolve site clearance, especially for public investment projects, growth-driving projects, and 151 delayed projects that already have specific plans; avoiding lingering obstacles extending into 2027 that could result in changes to compensation mechanisms and policies, causing difficulties for public mobilization. Concurrently, they must urgently put into effective exploitation and use the surplus housing, land, and public assets decentralized by the city for management; proactively base on the city's provisional capital notices and land auction revenues to promptly formulate and submit for approval the 2027 public investment plan.

For municipal departments and sectors, the Vice Chairman of the City People's Committee assigned the Department of Finance to closely follow developments, promptly advise on flexible capital reallocation between projects, and study incorporating disbursement pace into the capital allocation principles for the following year; the Department of Agriculture and Environment to coordinate with localities in urging industrial park and industrial cluster infrastructure developers to transfer site clearance funds, while reviewing land use fee calculations and the issuance of land use right certificates in resettlement areas; the Department of Construction to accelerate the appraisal and licensing of projects; the Department of Science and Technology to urgently upgrade the IOC system towards updating detailed lists of each project, attaching QR codes to track progress, and establishing automated warnings for delayed projects and localities to effectively serve the direction and administration of municipal leadership./.
Phuong Mai
Photo: Viet Cuong