(Haiphong.gov.vn) - On the morning of August 6, the Urban Committee of the City People's Council specifically supervised the implementation of Resolution No. 07/NQ-HDND dated April 12, 2024 of the City People's Council on the policy [...]

(Haiphong.gov.vn) - On the morning of August 6, the Urban Committee of the City People's Council specifically supervised the implementation of Resolution No. 07/NQ-HDND dated April 12, 2024 of the City People's Council on the investment policy of the Do Muoi Street construction investment project extending to the VSIP trunk road and urban development in the surrounding area at the Department of Transport. Comrade Phung Van Thanh, Head of the Urban Committee of the City People's Council, chaired the supervision. Also attending were representatives of relevant departments, branches, units and localities.

Work scene.
The investment project to build Do Muoi street extending to the VSIP trunk road and developing urban areas in the vicinity has a construction investment scale with a total length of 1,582m, the road level is the main road in the area, a design speed of 60km/h and creates a land fund for urban development in the surrounding area with a scale of 44,153 hectares in Thuy Nguyen district. Total project investment is 1,066 billion VND, from the city budget. Implementation time is from 2022 to 2024.
The project was implemented to promote the investment efficiency of the built Do Muoi route, improve traffic capacity, and connect the city center with Thuy Nguyen district. Carrying out land auctions, embellishment, and synchronous urban development of infrastructure throughout the North Cam River area, contributing to gradually completing the new City Center infrastructure system according to planning orientation, while creating new space on both sides of the road for urban development. Create a premise for socio-economic development, security and defense in the region.
>The supervision team inspected the field at Do Muoi street extending to the VSIP backbone.
To date, the project has been granted 27,765 million VND, disbursed 7,789,711 million VND (site clearance 3,679,717 million VND; construction 2,719,994 million VND; consulting costs and other costs are 1,390 million VND).
>Leaders of the Department of Transport reported at the meeting.
At the meeting, the Department of Transport requested the City People's Committee to consider and direct relevant agencies and units to carry out procedures for allocating land within the construction scope of Do Muoi street extending to the VSIP trunk road to the Department to pay money to protect and develop rice land according to regulations; Thuy Nguyen District People's Committee, VSIP Hai Phong Co., Ltd. handed over the site for construction of the intersection between Do Muoi Street and VSIP Street to the investor to begin construction.
>Comrade Phung Van Thanh, Head of the Urban Committee of the City People's Council, spoke at the meeting.
After inspecting the field and listening to reports from the project investor, relevant departments, branches and localities, Mr. Phung Van Thanh, Head of the Urban Committee of the City People's Council, highly appreciated the investor and the Project Management Board, Departments, branches and localities for closely coordinating, so the project was resolved problems and difficulties and implemented on schedule; Construction work is managed to ensure quality in accordance with the procedures and regulations of the law on construction investment; Disbursement progress is implemented to ensure on schedule. Comrade Head of the Urban Committee of the City People's Council requested relevant departments, branches and units to continue reviewing work contents to complete such as quality management, ensuring green trees, installing lighting systems and traffic lights; coordinate hCoordinate with local authorities to review and manage the order of house construction on both sides of the road according to the boundary lines and grant construction permits; Ensure payment and settlement according to regulations. At the same time, we request the Department of Transport to accept the comments of the Supervision Team to learn from experience in the process of establishing practical investment policies, especially in compensation and site clearance...